Serbia ponders penalties for Azvirt over Ljig-Preljina delays

The Serbian government has said it could issue penalties to the Azerbaijani construction company Azvirt for delays to work on the Ljig-Preljina Corridor 11 motorway project. Completion was set for the middle of next month. But last month the government said delays of around a month were due to problems construction the tunnel and bridge sections. The new route is expected to open around 40 days later than originally expected as a result.
September 9, 2016 Read time: 1 min

The Serbian government has said it could issue penalties to the Azerbaijani construction company 5414 Azvirt for delays to work on the Ljig-Preljina Corridor 11 motorway project.

Completion was set for the middle of next month. But last month the government said delays of around a month were due to problems construction the tunnel and bridge sections. The new route is expected to open around 40 days later than originally expected as a result.

Minister of Transport, Zorana Mihajlovic, had stated that the government will want an explanation from the investor, Serbian roads company 3235 Koridori Srbije.

For more information on companies in this article

Related Content

  • Serbia seals the deal for start of Belgrade Corridor 11 ring-road
    July 21, 2016
    Serbian vice president Zorana Mihajlovic has held talks with Li Manchang, China's Ambassador to Serbia in Serbia, for continuation of works on Belgrade’s ring road. According to the political magazine B92, Mihajlovic also signed a memorandum of understanding with Azvirt, the company from Azerbaijan, and China's Sinohidro. Discussions included continuation of work on the Surcin-Obrenovac part of the Corridor 11 motorway. A commercial deal for the project has already been signed with the China Communica
  • Serbia in talks with Chinese firms over Corridor 11 completion
    February 12, 2015
    Serbia will enter into talks with two Chinese companies chosen through a tender process that expired this month for restarting construction on the stalled Corridor 11 motorway. Serbian Minister of Construction Zorana Mihajlovic said Shandong Hi-Speed Group and the China Road and Bridge Corporation qualified for tender participation. Work includes construction and maintenance of 17.6km of motorway near Belgrade, between Surcin and Obrenovac as welll as the 31km Preljina-Pozega road and maintenance of t
  • Highway work planned for Serbia
    August 10, 2012
    A series of major highway construction and road repair projects is planned for Serbia. The World Bank (WB), the European Investment Bank (EIB) and the European Bank for Reconstruction and Development (EBRD) have all been in talks with the Serbian Government concerning funding for the work. Funding worth €408.46 million has been approved by the three banks for programme of highway construction and road repairs.
  • Progress on Serbia’s Zezeljev bridge replacement is slow
    August 30, 2017
    Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp