Progress on Serbia’s Zezeljev bridge replacement is slow

Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp
August 30, 2017 Read time: 2 mins

Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government.

Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported.

The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its campaign against Yugoslavia, of which Serbia was a member. The bridge was damaged first on 20 April 1999 and finally destroyed four days later, according to Edgar Martin, a waterways transportation consultant working in the Balkans.

Construction of the new bridge forms part of an 3287 EU strategy for the Danube Region. The replacement project was delayed initially because of work to remove wreckage of the old bridge in the Danube.

Completion of the bridge is not now likely to be in the spring of next year. Spanish company 5289 Azvi is the contractor and around €30 million of the estimated 60 million has been invested so far.

The minister also expressed concern over slow progress of works on Ub-Obrenovac part of the Corridor 11 motorway.

Serbia’s president Aleksandar Vucichas said he plans to visit the Surcin-Obrenovac section of Corridor 11. China Construction Communication Company began work on the 18km motorway in March 2017, with completion expected by the end of 2019. Value of works is estimated at €208 million, and is financed by China's Exim Bank, while Serbian roads company Putevi Srbije is the investor.

For more information on companies in this article

Related Content

  • Progress on Serbia’s Zezeljev bridge replacement is slow
    August 30, 2017
    Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp
  • New Zezelj’s Bridge in Novi Sad symbolises brotherhood and unity
    September 7, 2018
    The new Bridge of Brotherhood and Unity, also known as Zezelj’s Bridge, across the Danube River in Novi Sad, Serbia, is officially open. The road and rail tied-arch bridge replaces the original bridge of the same name that was built in 1961, named after the designer Branko Zezelj. The designer of the new bridge is Aleksandar Bojović and the contractor was an international consortium of Azvi, Taddei and Horta Coslada. One of the two arches is 177m long and 34m high and the other is 219m long and 42m high.
  • New Danube crossing for Serbia
    July 14, 2014
    In Serbia plans are moving ahead with work on the Zezeljev Bridge. The structure will provide a new crossing over the Danube River for the city of Novi Sad. The new bridge replaces an old structure carrying both rail and road links that was destroyed by bombing in 1999. Construction of the new bridge forms part of an EU strategy for the Danube Region. The current cost of the new bridge has not been disclosed although an estimate in 2010 pegged the pricetag at some €60million. The 470m long by 25m wide struc
  • Serbia’s pan-European Corridor X is in the slow lane
    October 23, 2017
    It’s been slow progress on Serbia’s Corridor X project. Gordon Feller reports. Back in the early 2000’s, the European Union undertook an ambitious programme to link the main cities of its south-eastern region. This involved connecting five key seaports – the Greek cities of Patras, Igoumenitsa, Piraeus and Thessaloniki as well as Romania’s Black Sea city of Constanta. Initially the plan involved two motorways across Greece. The first was a new 780km route including a branch to Ormenio on Greece’s north-eas