Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Completion of Prague’s outer ring-road Běchovice section for 2024
    July 24, 2019
    Completion of Prague’s outer ring-road connecting the D1 motorway with Běchovice town to the north should be in 2024, a year earlier than planned. Czech prime minister Andrej Babiš made the announcement, saying the 2025 date set by the Czech Highway Authority was too far off, according to local media. The national Czech News Agency reported that the 12.5km section will cost around €365 million. Transport minister Vladimíra Kremlík said that the state will have to acquire land from up to 500 land ow
  • Prague tunnel construction complete
    May 10, 2012
    Drilling work on the Blanka road tunnel in Czech capital Prague has now been completed. The new tunnel will become part of the Prague ring road once it is open to traffic. Construction commenced in 2007 but the project has faced a series of problems, including three collapses. The original cost was estimated at nearly €870 million for the construction works, €172 million for technology and €65 million for survey work. However, due to the problems the link has suffered the project is expected to cost close t
  • Causeway and immersed road for LagoonHull
    December 1, 2021
    The agency proposing the UK’s LagoonHull project says it’s development and construction costs could be between €1.2-2.4 billion.
  • Czech tenders for D6 section near Karlovy Vary
    June 7, 2023
    The Petrohrad-Lubenec section includes several bridges with work starting by the end of the year for completion in 2026.