Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Legal challenge to Australian road/tunnel connection
    July 23, 2014
    A legal challenge has been made to a key road and tunnel project in the Australian state of Victoria. The proposed East West link project is worth some US$5.63 billion in all. Local authorities are planning legal cases at the Supreme Court against the project, which includes a 4.4km stretch of tunnel. The package of works for the tunnel section is due to be signed in November 2014, with this link planned to open to traffic towards the end of 2019. It is not clear at this stage if the legal challenge will de
  • Highway 99 revisited
    March 6, 2024
    David Arminas recently returned to Seattle for an inside look at some of the features of the now-complete SR99 tunnel that was a World Highways key project report in November 2017.
  • More studies for the Great Istanbul Tunnel under the Bosporus
    March 11, 2019
    Work has started on a geological condition field study for a proposed 6.5km three-deck road and rail tunnel under the Bosporus Strait in Istanbul, Turkey. Average daily road traffic through the Great Istanbul Tunnel is expected to be 120,000 vehicles and the rail line will move around 75,000 people daily. The tunnel, announced in 2015, will be nearly 19m in diameter and have two road levels and one rail level. It will run between Gayrettepe on the European side and Küçüksu on the Asian side. The ci
  • Another Czech D6 tender due this autumn
    May 16, 2024
    Work on the section that will connect Bošov with Knínice will cost around €170 million.