Drilling work on the Blanka road tunnel in Czech capital Prague has now been completed. The new tunnel will become part of the Prague ring road once it is open to traffic. Construction commenced in 2007 but the project has faced a series of problems, including three collapses. The original cost was estimated at nearly €870 million for the construction works, €172 million for technology and €65 million for survey work. However, due to the problems the link has suffered the project is expected to cost close t
May 10, 2012 Read time: 1 min
Drilling work on the Blanka road tunnel in Czech capital Prague has now been completed. The new tunnel will become part of the Prague ring road once it is open to traffic. Construction commenced in 2007 but the project has faced a series of problems, including three collapses. The original cost was estimated at nearly €870 million for the construction works, €172 million for technology and €65 million for survey work. However, due to the problems the link has suffered the project is expected to cost close to €1.56 billion.

Related Content

  • Tunnel delays in Czech link
    February 27, 2012
    Drilling work on the Blanka road tunnel in Czech capital Prague has now been completed.
  • Leaks hit Czech Blanka Tunnel and boost costs
    July 26, 2013
    Further problems have hit the Blanka Tunnel in Czech capital Prague. The link has been hit by a series of delays and is now suffering from leaks. The project is costing €1.43 billion and is due to open in May 2014. The company building the tunnel Metrostav, has stated that the leaks are likely to be temporary and should be dealt with by the time the link opens to traffic, when it will become part of the Prague ring road. Construction work started on the tunnel in 2007 but the project has faced a series of p
  • Warm mix use in the US and Czech Republic is strong
    May 20, 2014
    The Czech Republic has seen its first ever use of warm mix produced using additive Evotherm - and a survey carried out in the US shows that warm mix is still on the rise there - Kristina Smith reports The troubled Blanka Tunnel in Prague will see the Czech Republic’s first ever use of Evotherm warm mix asphalt (WMA) technology. The 6km tunnel is the longest urban motorway tunnel in Europe and will take the north-west section of the city ring road below ground. Designed as dual carriageway throughout w
  • Prague wins legal battle over Blanka Tunnel costs
    September 6, 2016
    The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.