Mexico: Acapulco’s Escenica Alterna tunnel to open in 2017

Construction of the Escenica Alterna tunnel in the Mexican resort port city of Acapulco is expected to be finished by June 2017. Work started on the 3.1km tunnel in 2013 with completion originally scheduled for October 2015. But financial problems delayed the US$200 million project which is now around three-quarters complete. Work by the contractor IDEAL - part of conglomerate Grupo Carso - includes construction of an elevated road connecting tunnel with Metlapil motorway.
June 6, 2016 Read time: 1 min
Construction of the Escenica Alterna tunnel in the Mexican resort port city of Acapulco is expected to be finished by June 2017.

Work started on the 3.1km tunnel in 2013 with completion originally scheduled for October 2015. But financial problems delayed the US$200 million project which is now around three-quarters complete.

Work by the contractor 3136 IDEAL - part of conglomerate Grupo Carso - includes construction of an elevated road connecting tunnel with Metlapil motorway.

For more information on companies in this article

Related Content

  • Slovakia keeps to planned D1 Hubova-Ivachnova completion date
    August 19, 2019
    Slovakia’s national motorway company NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022. Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate. Montenegrin media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out
  • Singapore highway project planned
    April 12, 2017
    Delays have hit a major highway construction project in Singapore. Work on the 21.5km North-South Corridor was originally planned to start towards the end of 2017. However, construction will now commence in 2018. The delays to the start have been cauaed by the need for further revisions to the plans. When complete the new North-South Corridor highway will provide a connection between the northern region and the city. Despite the work starting later than planned, Singapore’s Land Transport Authority (LTA) be
  • Sao Paulo’s Mario Covas ring road faces last section glitch
    April 10, 2015
    A consortium of Brazil's Mendes Junior and Spain's Isolux Corsán could lose its US$208 million contract to build part of the northern section of the Mario Covas beltway around the Brazilian city of São Paulo. The consortium, led by Mendes Junior, is falling behind schedule because of cash flow problems, according to São Paulo state highway company Dersa. The deal was signed in January 2013, local paper Folha de São Paulo reported.
  • Fehmarnbelt Tunnel start looms on the horizon - 2020
    October 20, 2017
    Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company Femern. A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations. Baunkjaer noted that Denmark is all set to p