Delays plague Slovakia’s D1 motorway work

Slovakia is reporting delays to works on the D1 motor, the country’s major east-west corridor and part of several pan-European routes, including the E50. The planned 2020 completion of the D1 motorway linking Bratislava - Kosice could be 2021. There are reported technical complications to the section between Lietavska Lucka - Dubna Skala stretch with the Visnove tunnel near Zilina is experiencing complications. Work by the consortium of OHL and Vahostav on the D1 stretch Hubova – Ivachvova is suspended due
May 12, 2017 Read time: 1 min
Slovakia is reporting delays to works on the D1 motor, the country’s major east-west corridor and part of several pan-European routes, including the E50.


The planned 2020 completion of the D1 motorway linking Bratislava - Kosice could be 2021. There are reported technical complications to the section between Lietavska Lucka - Dubna Skala stretch with the Visnove tunnel near Zilina is experiencing complications.

Work by the consortium of 980 OHL and Vahostav on the D1 stretch Hubova – Ivachvova is suspended due to a land slide. Comlettion was to have been later this year, but this could be put back.

The D1 Hricovske Podhradie - Lietavska Lucka should be completed at the end of 2018.

European route E 50 runs from the France’s northern Atlantic naval port of Brest to Makhachkala, on the Caspian Sea in the Russian republic Dagestan.

For more information on companies in this article

Related Content

  • Slovakia’s D1 motorway Korbelka tunnel could cost €278mn
    August 19, 2016
    The D1 motorway tunnel Korbelka in Slovakia is estimated to now cost €278 million, according to a report in Pravda Slovakia. But the chosen 6km route is a safer option than another route alongside the Vah River that would have taken in a potential landslide area. Because of the slide risk, a further €202 million would be needed to shore up the hillside. More work will have to be done to finalise the route, meaning work would not start until likely 2019, according to the report. Slovakia's Transport
  • Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section
    December 13, 2017
    Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
  • Slovakia highway tunnel project – tendering to restart
    June 5, 2019
    The tender process will restart in 2019 for Slovakia’s Visnové Tunnel project. The tunnel forms part of the D1 highway. Work was being carried out on the tunnel and highway stretch of the D1 connecting Lietavska, Lucka, Visnové and Dubna Skala by the contractors Salini Impregilo and Duha. However following a dispute with the Slovak national motorway company NDS, these two firms are no longer working on the project. Some stretches of the highway are near complete already but the tunnel still requires some wo
  • STRABAG working on Slovakian highway
    December 16, 2013
    A consortium is now working on the construction of one stretch of Slovakia’s D1 highway. The section lies between Hričovské Podhradie and Lietavská Lúčka and the project is worth €427 million. The consortium comprises four companies; with Doprastav, Váhostav and STRABAG all holding equal 32% stakes of the contract and Metrostav having a minority 4% share. The work being carried out by Doprastav, Váhostav and STRABAG is equivalent to some €140 million each. The construction work is expected to take 48 months