Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • Slovakia’s Ruzomberok bypass and tunnel face severer delays
    September 4, 2017
    The bypass around the Slovakian town of Ružomberok, which was supposed to be finished this summer, faces a delay of more than four years. The bypass is part of a 15.2km stretch of the D1 highway between Hubová and Ivachnová. Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.
  • Slovakia keeps to planned D1 Hubova-Ivachnova completion date
    August 19, 2019
    Slovakia’s national motorway company NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022. Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate. Montenegrin media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out
  • Breakthrough near for Čebrať Tunnel
    December 17, 2021
    The 3.5km-long tunnel through Slovakia’s Čebrať Hills is part of the D1 Ružomberok bypass.
  • Slovakia tunnel sections underway but some delays
    January 23, 2018
    The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against th