Slovakia is reporting delays to works on the D1 motor, the country’s major east-west corridor and part of several pan-European routes, including the E50. The planned 2020 completion of the D1 motorway linking Bratislava - Kosice could be 2021. There are reported technical complications to the section between Lietavska Lucka - Dubna Skala stretch with the Visnove tunnel near Zilina is experiencing complications. Work by the consortium of OHL and Vahostav on the D1 stretch Hubova – Ivachvova is suspended due
May 12, 2017 Read time: 1 min
Slovakia is reporting delays to works on the D1 motor, the country’s major east-west corridor and part of several pan-European routes, including the E50.


The planned 2020 completion of the D1 motorway linking Bratislava - Kosice could be 2021. There are reported technical complications to the section between Lietavska Lucka - Dubna Skala stretch with the Visnove tunnel near Zilina is experiencing complications.

Work by the consortium of 980 OHL and Vahostav on the D1 stretch Hubova – Ivachvova is suspended due to a land slide. Comlettion was to have been later this year, but this could be put back.

The D1 Hricovske Podhradie - Lietavska Lucka should be completed at the end of 2018.

European route E 50 runs from the France’s northern Atlantic naval port of Brest to Makhachkala, on the Caspian Sea in the Russian republic Dagestan.

For more information on companies in this article

Related Content

  • Financial setbacks beset Slovakia’s highway development
    June 12, 2012
    Slovakian highway company NDS says that construction of the 13km Turany-Hubova highway may not be started in 2012. The previous Transport Ministry plan was to call the tender for this stretch in summer 2012. However, the EC has not yet approved the construction of this highway, with questions surrounding the protected area in the Velka and Mala Fatra mountains. If Slovakia does not get this approval, the country might have to chose the second option, which includes the tunnel Korbelka. The EC's decision is
  • Slovakia’s D1 highway project underway
    August 11, 2022
    Work on Slovakia’s D1 highway project is underway.
  • EU Cohesion Fund invests in Slovakia D1 motorway
    September 4, 2019
    The European Cohesion Fund is investing nearly €279 million in construction of the west-south deviation of the D1 motorway in Slovakia. The EU-funded works include construction of a two-way tunnel, two interchanges, 12 retaining walls, noise barriers and 18 bridges. The 515km cross-country D1 connects the capital Bratislava, along the Danube River close the country’s western border with the Czech Republic, and in the eastern city of Košice. An extension is proposed from Košice to Michalovce, further
  • Slovakian projects underway
    April 4, 2022
    Slovakian road projects are underway.