Atlanta airport’s new apron

The new Maynard H Jackson Jr International Terminal at Hartsfield- Jackson Atlanta International Airport is now open for business. The 111,484m2 terminal features 12 gates, eight security checkpoints, separate levels for arrivals and departures, as well as a 148,831m2 concrete apron for aircraft to park on arrival. Archer Western won the contract to slipform the concrete apron, replace the existing Taxiway D, as well as other utilities and embankment work. The firm brought in one of its GOMACO paving trains
October 12, 2012 Read time: 4 mins
Construction of the new terminal building was underway while the apron was being slipformed, resulting at times in job-site congestion while limiting paving production

The new Maynard H Jackson Jr International Terminal at Hartsfield- Jackson Atlanta International Airport is now open for business. The 111,484m2 terminal features 12 gates, eight security checkpoints, separate levels for arrivals and departures, as well as a 148,831m2 concrete apron for aircraft to park on arrival.

4760 Archer Western won the contract to slipform the concrete apron, replace the existing Taxiway D, as well as other utilities and embankment work. The firm brought in one of its 218 Gomaco paving trains, a PS-2600 placer/ spreader, a two-track GHP-2800 paver, and a T/C-600 texture/cure machine. A GOMACO Smoothness Indicator (GSI) machine followed the paving train, as this is required for all concrete paving projects at the airport, while a GOMACO 9500 placer was also used for hand pours on the apron.

The design of the apron dictated short paving runs, which limited daily slipform production. A 0.5% fall, to keep water from ponding on the apron, was also an exacting aspect of the project.

“Maintaining the 0.5% fall and keeping water from ponding on the new apron was one of the more difficult challenges,” said Justin Cooper, assistant project manager for Archer Western. “That is super flat and not a lot of room to play with. With the GSI, we were able to check the overall smoothness constantly and make sure our set-up was right on.”
The new apron was slipformed on top of a 229mm thick soil-cement sub-base,with concrete produced on-site by a mobile batch plant. The project used a standard P501 concrete with a low slump of 19mm and around 15 trucks were used to haul 7.6m3 concrete loads to the paving train.

“We used the PS-2600 on the project for the ride quality it gives us,” Cooper said. “We had good ride numbers using this stiff mix. The PS-2600 helped out and provided the initial knockdown of the concrete, which helped provide a nice smooth finish behind the GHP- 2800 paver.”

The GOMACO two-track GHP-2800 slipformed the apron in paving passes 7.6m wide and 508mm thick. Dowel baskets were placed on grade every 7.6m, with some areas of welded wire reinforcing depending on the shape of the slab.

“We had very little finishing work behind the paver and found the more we worked with the slab, the worse the numbers typically were,” Cooper said.

“The straight edging to adjacent lanes was important to ensure ponding water would not be held on the relatively flat apron.” Archer Western’s daily paving production was limited by the site layout.

The GOMACO 9500 placer was used in several areas for hand pours around embankment utilities, fuel pits, underdrains, and other various utilities. The firm also had to work around other contractors building the new terminal. Average slipform paving production was 1147m3/day, while the best production day reached 1529m3.

“The way the project was set up, the lanes weren’t long enough to have a really good day,” Cooper explained, adding that the firm did achieve 1376m3 and 1453m3 pours, “…but mostly we could only go as far as the lanes would take us.”
Finishing work behind the paver was kept to a minimum. The firm applied a burlap drag by hand and then used the GOMACO T/C-600 texture/cure machine to apply a white spray cure.

All of the new pavement was profiled by Archer Western’s GSI machine. The airport specification states that as soon as the concrete has hardened sufficiently, and within 24 hours of placement, the contractor will test the pavement surface.

Seven GSI units were mounted on the GSI machine, as required by the airport’s specification. The individual GSI units trace lines 305mm, 1.2m, and 2.4m off the joint line on each side, and also along the centerline of each 7.6m wide paving pass.

The airport also requires Archer Western to use a 4.9m rolling straight edge to check the new pavement. Surface deviations exceeding 6mm in 4.9m in any direction require correction. Any deviation over 13mm must be removed and replaced.

“On road projects we just run the sensors in the wheel paths, but since this is an airport project, the GSI is checking the entire width of the slab with seven sensors,” Cooper said. “It was definitely challenging, to say the least,” Cooper said. “We completed on time and delivered the project within spec. The airport in Atlanta is big on concrete paving and they make sure that we deliver the highest quality paving in the country at the airport.”

For more information on companies in this article

Related Content

  • Concrete paving meets demanding airport conditions
    July 11, 2012
    High speed, high quality concrete paving can be achieved in the demanding airport environment using the latest equipment. Minnich Manufacturing has developed a novel dowel pin drilling machine and has successfully tested this equipment at Tyndall Air Force Base in Panama City, Florida. The A-5SCW is a self-propelled, cantilevered machine that features a wireless remote control and is designed to install five dowel pins simultaneously. The control system has been developed by Wisconsin Kar-Tech and uses prov
  • THIS is a Paving Project– The I-15 CORE
    December 20, 2012
    Provo, Utah – The scope of the I-15 Corridor Expansion Project (I-15 CORE) in the state of Utah is nearly unprecedented because of the size of the project and the short completion deadline. Twenty-four miles (38.6 km) of removal and replacement of Interstate 15 between Lehi and Spanish Fork, widening the number of traveling lanes by two, for up to six lanes in each direction in 35 months. The new 364 lane miles (586 km) of concrete roadway will be slipformed 12 or 12.5 inches (305 or 318 mm) thick for a tot
  • Efficient concrete overlays
    February 15, 2012
    Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay. Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage. CFI has slipformed most of the overlays with its GOMACO two-track GP-2600 paver. This season, the co
  • New concrete surface for Arizona freeway
    November 15, 2013
    In Tucson, Arizona, contractor McNeil brothers is using a two-track GOMACO concrete slipformer on a 3.2km stretch of highway. This project is for the Arizona Department of Transportation (ADOT) and involves widening Interstate 10 to four lanes of traffic in each direction between Ruthrauff Road and Prince Road in Tucson. This new stretch was needed to better handle increasing traffic demands in the city and includes rebuilt entrance and exit ramps to improve access to the city.