Atlanta airport’s new apron

The new Maynard H Jackson Jr International Terminal at Hartsfield- Jackson Atlanta International Airport is now open for business. The 111,484m2 terminal features 12 gates, eight security checkpoints, separate levels for arrivals and departures, as well as a 148,831m2 concrete apron for aircraft to park on arrival. Archer Western won the contract to slipform the concrete apron, replace the existing Taxiway D, as well as other utilities and embankment work. The firm brought in one of its GOMACO paving trains
October 12, 2012 Read time: 4 mins
Construction of the new terminal building was underway while the apron was being slipformed, resulting at times in job-site congestion while limiting paving production

The new Maynard H Jackson Jr International Terminal at Hartsfield- Jackson Atlanta International Airport is now open for business. The 111,484m2 terminal features 12 gates, eight security checkpoints, separate levels for arrivals and departures, as well as a 148,831m2 concrete apron for aircraft to park on arrival.

4760 Archer Western won the contract to slipform the concrete apron, replace the existing Taxiway D, as well as other utilities and embankment work. The firm brought in one of its 218 Gomaco paving trains, a PS-2600 placer/ spreader, a two-track GHP-2800 paver, and a T/C-600 texture/cure machine. A GOMACO Smoothness Indicator (GSI) machine followed the paving train, as this is required for all concrete paving projects at the airport, while a GOMACO 9500 placer was also used for hand pours on the apron.

The design of the apron dictated short paving runs, which limited daily slipform production. A 0.5% fall, to keep water from ponding on the apron, was also an exacting aspect of the project.

“Maintaining the 0.5% fall and keeping water from ponding on the new apron was one of the more difficult challenges,” said Justin Cooper, assistant project manager for Archer Western. “That is super flat and not a lot of room to play with. With the GSI, we were able to check the overall smoothness constantly and make sure our set-up was right on.”
The new apron was slipformed on top of a 229mm thick soil-cement sub-base,with concrete produced on-site by a mobile batch plant. The project used a standard P501 concrete with a low slump of 19mm and around 15 trucks were used to haul 7.6m3 concrete loads to the paving train.

“We used the PS-2600 on the project for the ride quality it gives us,” Cooper said. “We had good ride numbers using this stiff mix. The PS-2600 helped out and provided the initial knockdown of the concrete, which helped provide a nice smooth finish behind the GHP- 2800 paver.”

The GOMACO two-track GHP-2800 slipformed the apron in paving passes 7.6m wide and 508mm thick. Dowel baskets were placed on grade every 7.6m, with some areas of welded wire reinforcing depending on the shape of the slab.

“We had very little finishing work behind the paver and found the more we worked with the slab, the worse the numbers typically were,” Cooper said.

“The straight edging to adjacent lanes was important to ensure ponding water would not be held on the relatively flat apron.” Archer Western’s daily paving production was limited by the site layout.

The GOMACO 9500 placer was used in several areas for hand pours around embankment utilities, fuel pits, underdrains, and other various utilities. The firm also had to work around other contractors building the new terminal. Average slipform paving production was 1147m3/day, while the best production day reached 1529m3.

“The way the project was set up, the lanes weren’t long enough to have a really good day,” Cooper explained, adding that the firm did achieve 1376m3 and 1453m3 pours, “…but mostly we could only go as far as the lanes would take us.”
Finishing work behind the paver was kept to a minimum. The firm applied a burlap drag by hand and then used the GOMACO T/C-600 texture/cure machine to apply a white spray cure.

All of the new pavement was profiled by Archer Western’s GSI machine. The airport specification states that as soon as the concrete has hardened sufficiently, and within 24 hours of placement, the contractor will test the pavement surface.

Seven GSI units were mounted on the GSI machine, as required by the airport’s specification. The individual GSI units trace lines 305mm, 1.2m, and 2.4m off the joint line on each side, and also along the centerline of each 7.6m wide paving pass.

The airport also requires Archer Western to use a 4.9m rolling straight edge to check the new pavement. Surface deviations exceeding 6mm in 4.9m in any direction require correction. Any deviation over 13mm must be removed and replaced.

“On road projects we just run the sensors in the wheel paths, but since this is an airport project, the GSI is checking the entire width of the slab with seven sensors,” Cooper said. “It was definitely challenging, to say the least,” Cooper said. “We completed on time and delivered the project within spec. The airport in Atlanta is big on concrete paving and they make sure that we deliver the highest quality paving in the country at the airport.”

For more information on companies in this article

Related Content

  • G&Z paving Canada’s longest runway
    October 12, 2012
    A contractor in Canada, Dufferin Construction, is using three items of new equipment bought from Guntert & Zimmerman to pave the country’s longest runway. The project is extensive, featuring a new runway measuring 4.3km long by 60m wide, an apron area measuring 145,000m2 and two taxiways, each 3.8km long by 25m wide. In all, the work requires 1.5 million tonnes of base aggregate, and 200,000m2 of cement-stabilised base. Dufferin Construction Company, a division of Holcim (Canada) already owns two other G&Z
  • Machine control used for road revamp for Arkansas highway
    June 23, 2015
    A historic route in the US state of Arkansas has benefited from the use of machine control during its upgrade The south-west - north-east US Route 67 in Arkansas has long been a significant transport route. This old road follows the natural break between the Ozark Mountains and the Ouachita Mountains. In the 1920s, funding became available for road paving, and the route was designated US Route 67.
  • Thin surface whitetopping for busy roads
    April 5, 2017
    In the US, considerable experience has been gained with thin white-topping (TWT), with the technique now being used in other countries as well. In the US hundreds of km of TWT is being paved every year, much of it across the mid-western states. A variation of white-topping is being used in Oregon to replace badly rutted asphalt truck lanes on primarily long uphill grades with durable, continuously reinforced concrete pavement (CRCP). Oregon has carried out several of these concrete inlay projects over the
  • Concrete paving key to Berlin's airport runways
    February 17, 2012
    High production concrete paving is proving a key feature at the new Berlin airport facility currently under construction The new Berlin-Brandenburg International Airport will soon provide improved links by air to the city. Work started in mid 2006 with the redevelopment of the existing Berlin Schönefeld Airport.