Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay. Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage. CFI has slipformed most of the overlays with its GOMACO two-track GP-2600 paver. This season, the co
February 15, 2012 Read time: 2 mins
Efficient concrete overlays are being achieved with the use of stringless controls

Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay.

Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage.

CFI has slipformed most of the overlays with its 218 Gomaco two-track GP-2600 paver. This season, the company added the Leica Geosystems stringless system and a new GOMACO four-track GHP-2800 paver to the inventory. Both were put to work on the project near Osage.

The new unbonded concrete overlay is 6.7m wide, and the material is placed directly on the existing asphalt surface of the roadway. The surface only has to be swept clean before the mix is dumped on it and concrete slump averages around 13-25mm.

The firm has seen increased production with fewer people needed for stringline maintenance and setup. Five site personnel who normally worked with the stringline are now used elsewhere during the paving process. The lack of stringline also allows them to focus more on quality and production rather than stringline maintenance.

The GOMACO GHP-2800 is pulling burlap for a burlap drag finish behind the paver. Finishers work behind the paver with bull floats before a texture/cure machine applies a longitudinal tine and white spray cure.

For more information on companies in this article

Related Content

  • Concrete surface for runway paving job
    January 18, 2016
    The Fort Lauderdale-Hollywood International Airport in Broward County, Florida, was suffering departure delays on every single flight. The existing 9R-27L runway was too short at 1615m in length, affecting capacity at the airport. To deal with the issue, the Broward County Board of County Commissioners created a plan to extend the southern runway to 2438m to accommodate larger commercial aircraft. The project was not simple however and could not be achieved by tearing out the existing runway and buil
  • Gomaco smooth the way for new NY State concrete highway
    April 2, 2014
    When New York State Thruway wanted to experiment with unbonded concrete overlays, they chose an 8km, four-lane section of Interstate 90 near Hamburg as their test section. Surianello General Concrete, based in Buffalo, New York, won the bid to pave the 22.9cm thick concrete overlay. The age and the design of the original roadway created a major paving challenge. It was built in the 1950s and didn’t conform to current geometry requirements for superhighways. “They built it with a standard crown sectio
  • Machine control technology allows more efficient paving
    March 3, 2015
    In the US, a specialist contractor is making savings with new 3D technology for concrete paving. US contractor Gehring Construction is a specialist in concrete paving and is a long-time customer of GOMACO. Having bought its first GOMACO unit in 1973, Gehring has a good deal of experience in this segment. The company is now using some of the latest machine control technology, having bought a Topcon Millimetre GPS 3D stringless system, which has been used on a bypass project around the US city of Colombus. T
  • New concrete surface for Arizona freeway
    November 15, 2013
    In Tucson, Arizona, contractor McNeil brothers is using a two-track GOMACO concrete slipformer on a 3.2km stretch of highway. This project is for the Arizona Department of Transportation (ADOT) and involves widening Interstate 10 to four lanes of traffic in each direction between Ruthrauff Road and Prince Road in Tucson. This new stretch was needed to better handle increasing traffic demands in the city and includes rebuilt entrance and exit ramps to improve access to the city.