Montreal’s new Champlain Bridge is in a race against time

Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General. The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path. The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate. The government signed a contract in 2015 with a private
June 8, 2018 Read time: 2 mins
Touch and go for Montreal’s Champlain Bridge (photo: courtesy Signature on the St Lawrence - December 2016)

Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General.

The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path.

The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate.

The government signed a contract in 2015 with a private partner, Signature on the Saint Lawrence Group led by Canada-based SNC-Lavalin Group, to deliver the project for just under $3 billion, excluding the government’s project management and land acquisition costs. The contract called for the new bridge to be ready for use by 1 December, according to the Auditor General’s report.

It included a 42-month construction period and a 30-year operation and maintenance period. Other sections of the project were scheduled to come into use by 31 October 2019.

Among the criticisms made by Auditor General was the federal government’s slow decision to invest in a new bridge instead of maintaining the existing one.

“This matters because the delay in decision making entailed avoidable expenditures of more than [$385 million], apart from the economic costs to the greater Montréal area due to the congestion and load limitations on the existing bridge,” the report says.

The report also criticised government’s Infrastructure Canada department for completing its analysis of procurement models for the project two years after it announced the choice of a public-private partnership model.

“If the department had thoroughly analysed the procurement models for the project, it would have found that the public-private partnership could be more expensive than a traditional model.”

The Auditor General of Canada conducts independent audits of federal government projects and operations. It reports to the House of Commons of Canada, not to the government. The audits provide members of Parliament with objective information to help them examine the government's activities and hold it to account.

Related Content

  • SSL settles legal issues, Champlain Bridge to open December 21
    April 18, 2018
    Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
  • Ramboll appointed independent engineer on Champlain Bridge Project
    September 8, 2015
    Ramboll has been appointed independent engineer for the planned Champlain Bridge Corridor project in Montreal, Canada. Ramboll, based in Denmark, will work with the Canadian consultant Stantec to review the design and construction schedule of the entire length of the bridge corridor, one of the largest infrastructure projects in North America. Stantec will review of all highway design along with site inspections for the project that will cross the St. Lawrence River and cost up to US$4.1 billion. “The ne
  • Champlain Bridge set to open by end of year, says SNC-Lavalin
    March 6, 2018
    The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
  • Champlain Bridge consortium files lawsuit
    October 25, 2021
    Signature on the Saint Lawrence claims the Canadian federal government passed a large part of additional costs onto SSL.