Champlain Bridge consortium files lawsuit

Signature on the Saint Lawrence claims the Canadian federal government passed a large part of additional costs onto SSL.
By David Arminas October 25, 2021 Read time: 2 mins
The new Samuel De Champlain Bridge has six vehicle lanes plus two lanes in the middle of for electric commuter trains (image courtesy SSL)

The consortium that oversaw construction of the Champlain Bridge has filed a lawsuit against the federal government claiming it failed to honour its contract.

Signature on the Saint Lawrence consortium, that includes SNC-Lavalin, ACS Infrastructure and Hochtief PPP Solutions, said that the Canadian federal government passed a large part of additional costs onto SSL, according to a report in the Toronto Star newspaper.
       
The lawsuit for nearly US$302 million (€256.7 million) noted that the old bridge near Montreal in the province of Quebec would be used for transporting construction material for the new bridge being built close be. But in 2016 the provincial agency Transports Quebec imposed significant weight limits for trucks forcing the consortium to resort to barging in supplies which raised construction costs and interfered with the timetable.

Even before this, in September 2015, six months after the partnership contract was signed, the government decided to abolish tolling on the bridge. It was a decision that had financial implications for the consortium that had signed only several months before a public-private partnership deal worth US$34 billion and with a scheduled opening of December 1, 2018. The 3.4km bridge – of a 6km corridor that was constructed - finally opened in June 2019.

Infrastructure Canada, the federal agency responsible for the public-private partnership, denied not having honoured its end of the contract and remains committed to working with SSL.

The new Samuel De Champlain Bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles crossed the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

For more information on companies in this article

Related Content

  • SSL settles legal issues, Champlain Bridge to open December 21
    April 18, 2018
    Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
  • Champlain Bridge set to open by end of year, says SNC-Lavalin
    March 6, 2018
    The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
  • Champlain Bridge set to open by end of year, says SNC-Lavalin
    May 14, 2018
    The Canadian city’s replacement Champlain Bridge will open on schedule at the end of the year. Montreal, one of Canada’s largest cities, will have a well-earned Christmas present in December when the new Champlain Bridge opens after 42 months of construction. The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, runs from the île des Soeurs to Brossard, immediately dow
  • Montreal’s Champlain Bridge opens but late and over-budget
    June 27, 2019
    Montreal’s US$3.5-billion, 3.4km-long Samuel de Champlain Bridge has opened after four years of construction and months of delays, according to Canadian media reports. Work is continuing on the cycle and pedestrian paths and eventually a light-rail train will run down the middle of the six lane bridge over the St. Lawrence River. The new structure has a life-span of 125 years and runs alongside its namesake Champlain Bridge, a steel truss cantilever that opened in 1962 which will be demolished. Accord