Champlain Bridge consortium files lawsuit

Signature on the Saint Lawrence claims the Canadian federal government passed a large part of additional costs onto SSL.
By David Arminas October 25, 2021 Read time: 2 mins
The new Samuel De Champlain Bridge has six vehicle lanes plus two lanes in the middle of for electric commuter trains (image courtesy SSL)

The consortium that oversaw construction of the Champlain Bridge has filed a lawsuit against the federal government claiming it failed to honour its contract.

Signature on the Saint Lawrence consortium, that includes SNC-Lavalin, ACS Infrastructure and Hochtief PPP Solutions, said that the Canadian federal government passed a large part of additional costs onto SSL, according to a report in the Toronto Star newspaper.
       
The lawsuit for nearly US$302 million (€256.7 million) noted that the old bridge near Montreal in the province of Quebec would be used for transporting construction material for the new bridge being built close be. But in 2016 the provincial agency Transports Quebec imposed significant weight limits for trucks forcing the consortium to resort to barging in supplies which raised construction costs and interfered with the timetable.

Even before this, in September 2015, six months after the partnership contract was signed, the government decided to abolish tolling on the bridge. It was a decision that had financial implications for the consortium that had signed only several months before a public-private partnership deal worth US$34 billion and with a scheduled opening of December 1, 2018. The 3.4km bridge – of a 6km corridor that was constructed - finally opened in June 2019.

Infrastructure Canada, the federal agency responsible for the public-private partnership, denied not having honoured its end of the contract and remains committed to working with SSL.

The new Samuel De Champlain Bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles crossed the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

For more information on companies in this article

Related Content

  • Montreal’s Champlain Bridge superstructure deal signed with Canam-Bridge
    May 22, 2015
    Canada-based Canam-Bridge has been chosen to fabricate the superstructure for the Champlain bridge project in Montreal as well as to supply steel. Marc Dutil, chief executive of Canam, a specialist bridge superstructure fabricator, expects at least 45,000tonnes of steel will be required for the 3.4km bridge that will span the St. Lawrence River which leads to the Great Lakes of North America. The contract is expected to be completed after a formal deal is reached between the SNC-Lavalin consortium con
  • Canada: work officially starts on Montreal’s Champlain Bridge
    June 25, 2015
    Canada’s infrastructure minister, Denis Label, officially broke ground for Montreal’s replacement Champlain Bridge, saying the project will likely cost US$3.42 billion. The 3.4km Champlain Bridge Corridor Project, including spans and highway expansions, is expected to be completed by 2019. SNC-Lavalin, the 50% stakeholder in the winning consortium Signature on the Saint-Lawrence, recently announced it had finalised the deal with new Champlain Bridge owner Infrastructure Canada. Signature on the Saint-
  • Ramboll appointed independent engineer on Champlain Bridge Project
    September 8, 2015
    Ramboll has been appointed independent engineer for the planned Champlain Bridge Corridor project in Montreal, Canada. Ramboll, based in Denmark, will work with the Canadian consultant Stantec to review the design and construction schedule of the entire length of the bridge corridor, one of the largest infrastructure projects in North America. Stantec will review of all highway design along with site inspections for the project that will cross the St. Lawrence River and cost up to US$4.1 billion. “The ne
  • Quebec to build new Mercier Bridge for Montreal city
    May 12, 2017
    The Canadian province of Quebec plans to build a US$219 million bridge across the St Lawrence River alongside the existing Mercier Bridge in the city of Montreal. Provincial government cabinet ministers Pierre Moreau and Geoff Kelley confirmed that a new bridge is forthcoming, but gave schedule for procurement or construction start, according to local media. However, Moreau said the work will begin probably before the new Champlain Bridge is finished at the start of 2019. Construction of the new Champlain B