Czech bypass project faces delay

An important Czech bypass project is facing delays.
By MJ Woof September 18, 2020 Read time: 1 min
An important bypass project in the Czech Republic is now facing delays - image © courtesy of Artof Sha, Dreamstime.com
Delays are now affecting construction work for the Czech Republic’s Ceske Budejovice bypass project. As a result, the bypass will not be ready for traffic until 2024.

Geological problems in the Pohurka Tunnel are at the heart of the delays. Dealing with unexpectedly high levels of groundwater will add around €3.88 million to the project. In all, the project is costing around 204.9 million.

Related Content

  • South German road tunnel project to restart
    July 26, 2018
    Construction work on the Kramertunnel in South Germany is to restart. The tunnel is needed to help reduce traffic delays in the town of Garmisch-Partenkirchen in the southern German state of Bavaria and with lies next to the border with Austria. The twin tube tunnel stretches will both be around 2.8km long and the project will also include building six bridges as part of the new bypass around the town. The new bypass, with its tunnel and bridges, is required as traffic jams occur regularly in the town on th
  • Colombia tunnel delays continue
    September 26, 2016
    Further delays have hit the project to build the La Linea Road Tunnel in Colombia. As a result the tunnel will not be open to traffic until the first half of 2018. This is the latest in a series of delays that have held back the opening of the tunnel. Previous delays have been caused by the discovery of geological conditions that were far more challenging than originally expected as well as problems over insurance cover for the construction firms. When open to traffic the new link will stretch 8.6km and wil
  • Slovakia tunnel sections underway but some delays
    January 23, 2018
    The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against th
  • Colombia’s La Linea Tunnel project delayed
    August 22, 2018
    A tale of woe surrounds Colombia’s La Linea Tunnel project, which is still incomplete. The project has been beset by a serious of issues including unexpectedly poor geological conditions, contractors having the wrong kind of insurance, insufficient funds for work to continue and in more recent times, further geological problems. While the Tolima end of the link is now close to completion, work still remains to be done at the Quindio end of the tunnel. Measuring 315m long, the La Gata section is now largely