South German road tunnel project to restart

Construction work on the Kramertunnel in South Germany is to restart. The tunnel is needed to help reduce traffic delays in the town of Garmisch-Partenkirchen in the southern German state of Bavaria and with lies next to the border with Austria. The twin tube tunnel stretches will both be around 2.8km long and the project will also include building six bridges as part of the new bypass around the town. The new bypass, with its tunnel and bridges, is required as traffic jams occur regularly in the town on th
July 26, 2018 Read time: 2 mins
Construction work on the Kramertunnel in South Germany is to restart. The tunnel is needed to help reduce traffic delays in the town of Garmisch-Partenkirchen in the southern German state of Bavaria and with lies next to the border with Austria. The twin tube tunnel stretches will both be around 2.8km long and the project will also include building six bridges as part of the new bypass around the town. The new bypass, with its tunnel and bridges, is required as traffic jams occur regularly in the town on the existing road. Heavy trucks and holiday traffic crossing the border with Austria can cause congestion.


The project is expected to cost €198 million, with €40 million already having been spent on works carried out so far. Only 350m of the emergency tunnel still needs to be completed. Work commenced in 2010 but was halted in 2013 due to the presence of large quantities of water  in the strata. A new design is being used to cope with the presence of water and the Kramertunnel should be ready for traffic by 2024.

The tunnel sections are being driven using conventional drilling and blasting methods for the hard rock sections comprising around 80% of the length, and with excavators for the looser materials in the remaining 20%. Conventional rock support methods are being used with shotcreting and rock bolting and bolted pre-cast liners. Additional rock support is being used where needed also, while the design now includes extra waterproofing and suitable drainage with collection basins to handle the groundwater and meet environmental requirements. Connecting tunnel sections are located at 500m intervals to meet safety requirements.

Related Content

  • Tunnel project for south German town to restart
    August 5, 2019
    Construction work is to restart on a new tunnel project in the South German town of Garmisch-Partenkirchen following the necessary approvals having been received. The town lies to the south of Munich and is a popular winter ski resort, while in summer it also experiences heavy tourist traffic as it lies on a key route between Germany and Austria, as well as Italy, lying to the south. The busy Autobahn 95 connects Munich’s southern side with Garmisch-Partenkirchen. But this route ends just to the northern si
  • Bavarian road tunnel opens to traffic
    June 1, 2022
    A new Bavarian road tunnel is now open to traffic
  • Italy road tunnel project excavated
    July 9, 2018
    Italy’s A3 Highway is being upgraded, which will improve transport between Salerno and Calabria. Upgrading Italy’s A3 highway is of prime importance for developing the south of the country and is a project that has been prioritised for construction. The A3 Salerno-Reggio-Calabria highway is a non-toll road managed by ANAS, Italy’s state-owned company that constructs and maintains highways. The route runs a total of 443km, with the road having originally been built between 1966 and 1974. However, the origina
  • Major Necaxa-Tihuatlan Highway project for Mexico
    October 1, 2014
    A new highway in Mexico is connecting Necaxa with Tihuatlan and the project features challenging terrain - Mauro Nogarin reports In Mexico a landmark highway project is now close to completion, having set a number of records for Latin America.