Colombia’s La Linea Tunnel project delayed

A tale of woe surrounds Colombia’s La Linea Tunnel project, which is still incomplete. The project has been beset by a serious of issues including unexpectedly poor geological conditions, contractors having the wrong kind of insurance, insufficient funds for work to continue and in more recent times, further geological problems. While the Tolima end of the link is now close to completion, work still remains to be done at the Quindio end of the tunnel. Measuring 315m long, the La Gata section is now largely
August 22, 2018 Read time: 2 mins

A tale of woe surrounds Colombia’s La Linea Tunnel project, which is still incomplete. The project has been beset by a serious of issues including unexpectedly poor geological conditions, contractors having the wrong kind of insurance, insufficient funds for work to continue and in more recent times, further geological problems.

While the Tolima end of the link is now close to completion, work still remains to be done at the Quindio end of the tunnel. Measuring 315m long, the La Gata section is now largely finished. However geological problems with the 165m El Viento section are not likely to be resolved until the end of 2018.

Surfacing work remains to be carried out while installation of some of the steel support arches is running behind schedule. The surfacing work should be complete by May 2019. The ventilation, lighting and traffic control systems have yet to be installed.

Related Content

  • Colombia’s La Linea Tunnel will be completed
    September 16, 2015
    Colombia's national road institute (Invias) has said that the La Linea tunnel project will open to traffic in 2017. The project has been delayed on several occasions and due to a variety of reasons, presenting a luckless and lengthy tale of woe for Colombia’s transport ministry. Early in its lifetime the project was held back by unexpected geological issues arising from more challenging ground conditions than had been initially realised. The project was also delayed by insurance problems for some of the fir
  • Colombia’s La Linea Tunnel completion in sight
    May 7, 2015
    The completion of Colombia’s long-running La Linea Tunnel project is now in sight, finally. Colombia’s president, Juan Manuel Santos, and vice president, German Vargas Lleras, made a joint announcement that the 8.65km long tunnel will be inaugurated in November 2016. The two tunnel drives (from Quindio and Tolima) have now met in the middle and only lining works are left to be completed. Once the tunnel is operational, it will enable trucks to complete the journey between Cajamarca (Tolima) and Calarca (Qui
  • Colombia’s delayed La Linea Tunnel and tertiary road development programme seeing progress
    July 6, 2017
    Progress is now being seen in Colombia with regard to key tunnel and road projects. A consortium comprising Conconcreto and CSS Constructores is to complete the 12% of work still needed to finish the La Linea Tunnel project.
  • Key Colombia tunnel projects delayed
    September 21, 2018
    Construction work on Colombia’s two key tunnel projects is being delayed, with insufficient funding proving a major challenge. Both the Toyo Tunnel and La Linea Tunnel projects are behind schedule. In addition, the project to construct the Pumajero Bridge is also being delayed due to a lack of funds.Part of the problems is that the designs for these projects have been revised as construction work has progressed. However the additional funds to pay for the new design features added have not been fully