Colombia’s La Linea Tunnel link opening

Colombia’s La Linea Tunnel link is opening to traffic.
By MJ Woof September 1, 2020 Read time: 1 min
Colombia’s delayed La Linea Tunnel link is now opening to vehicles at last - image © courtesy of Wollertz, Dreamstime.com

In Colombia the long awaited La Linea tunnel link is opening to traffic. The tunnel project has been subject to a string of delays since excavation work commenced. Geological problems and insufficient funding have held back the opening of the tunnel.

With the tunnel open, it will for part of the Cruce de la Cordillera Central route. In all, four tunnels, five bridges and two interchanges are opening to drivers The total length of road opening measures 13.4km in dual carriageway format.

The new connection will improve journey times for drivers along the route, as well making a considerable boost to safety.

 

Related Content

  • El Sillar – Bolivia’s challenging road project
    February 6, 2020
    Construction of Bolivia’s El Sillar highway, the country’s most complicated road project – Mauro Nogarin reports
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.
  • Further delays possible for Colombia tunnel
    July 21, 2016
    Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
  • Colombia tunnel construction contract commencing
    February 5, 2018
    Driving work has commenced for Colombia’s Toro Tunnel project. The tunnel will measure 9.8km long and is located in Colombia’s Antioquia Department, with the completion expected in 2022. The project is costing US$650.5 million and the link is intended to provide a link between the Autopista al Mar 1 and Autopista al Mar 2 highways. When complete the tunnel will also cut the travel time between Medellin and Uraba to four hours.