Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Colombia key tunnel project – new completion date
    March 6, 2019
    A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
  • Colombia’s tunnel of woe faces further setback
    May 19, 2017
    The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to
  • Colombia’s La Linea Tunnel will be completed
    September 16, 2015
    Colombia's national road institute (Invias) has said that the La Linea tunnel project will open to traffic in 2017. The project has been delayed on several occasions and due to a variety of reasons, presenting a luckless and lengthy tale of woe for Colombia’s transport ministry. Early in its lifetime the project was held back by unexpected geological issues arising from more challenging ground conditions than had been initially realised. The project was also delayed by insurance problems for some of the fir
  • Interest strong for Colombia key tunnel project
    January 22, 2019
    Interest is strong in the project to complete Colombia’s key tunnel construction contract. In all 23 firms have shown interest in the package of works to complete the La Linea tunnel project, according to the Colombian national road institute (Invias). The Colombian Government is providing US$204.5 million to complete the project. The current target is for the tunnel to be completed by 2020, although the link was originally supposed to be ready for traffic in late 2016. Construction work on the link commenc