Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Interest strong for Colombia key tunnel project
    January 22, 2019
    Interest is strong in the project to complete Colombia’s key tunnel construction contract. In all 23 firms have shown interest in the package of works to complete the La Linea tunnel project, according to the Colombian national road institute (Invias). The Colombian Government is providing US$204.5 million to complete the project. The current target is for the tunnel to be completed by 2020, although the link was originally supposed to be ready for traffic in late 2016. Construction work on the link commenc
  • Further delays possible for Colombia tunnel
    July 21, 2016
    Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
  • Colombia’s tunnel of woe faces further setback
    May 19, 2017
    The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to
  • Colombia road projects delivered
    September 24, 2020
    Important road projects in Colombia have been delivered successfully.