In Colombia the long awaited La Linea tunnel link is opening to traffic. The tunnel project has been subject to a string of delays since excavation work commenced. Geological problems and insufficient funding have held back the opening of the tunnel.

With the tunnel open, it will for part of the Cruce de la Cordillera Central route. In all, four tunnels, five bridges and two interchanges are opening to drivers The total length of road opening measures 13.4km in dual carriageway format.

The new connection will improve journey times for drivers along the route, as well making a considerable boost to safety.

 

Related Content

  • Interest strong for Colombia key tunnel project
    January 22, 2019
    Interest is strong in the project to complete Colombia’s key tunnel construction contract. In all 23 firms have shown interest in the package of works to complete the La Linea tunnel project, according to the Colombian national road institute (Invias). The Colombian Government is providing US$204.5 million to complete the project. The current target is for the tunnel to be completed by 2020, although the link was originally supposed to be ready for traffic in late 2016. Construction work on the link commenc
  • Colombia’s La Linea Tunnel will be completed
    September 16, 2015
    Colombia's national road institute (Invias) has said that the La Linea tunnel project will open to traffic in 2017. The project has been delayed on several occasions and due to a variety of reasons, presenting a luckless and lengthy tale of woe for Colombia’s transport ministry. Early in its lifetime the project was held back by unexpected geological issues arising from more challenging ground conditions than had been initially realised. The project was also delayed by insurance problems for some of the fir
  • Colombia key tunnel project – new completion date
    March 6, 2019
    A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
  • Colombia’s key tunnel – completion date set?
    January 11, 2019
    Colombia has set a new date for the completion of the La Linea tunnel project of May 2020. The project has been subject to a series of delays due to issues such as insufficient financing, unexpected geological problems and even the wrong type of insurance cover. The completion date for the main tunnel stretch has been moved back several times, but it is hoped that it will finally be completed on the date, which was announced by Colombia’s president, Ivan Duque. The completion of the entire project, whic