Colombia’s La Linea Tunnel link opening

Colombia’s La Linea Tunnel link is opening to traffic.
By MJ Woof September 1, 2020 Read time: 1 min
Colombia’s delayed La Linea Tunnel link is now opening to vehicles at last - image © courtesy of Wollertz, Dreamstime.com

In Colombia the long awaited La Linea tunnel link is opening to traffic. The tunnel project has been subject to a string of delays since excavation work commenced. Geological problems and insufficient funding have held back the opening of the tunnel.

With the tunnel open, it will for part of the Cruce de la Cordillera Central route. In all, four tunnels, five bridges and two interchanges are opening to drivers The total length of road opening measures 13.4km in dual carriageway format.

The new connection will improve journey times for drivers along the route, as well making a considerable boost to safety.

 

Related Content

  • Colombia dual carriageway concession awarded
    January 29, 2021
    A key Colombian dual carriageway concession has been awarded.
  • Colombia’s La Linea Tunnel project delayed
    August 22, 2018
    A tale of woe surrounds Colombia’s La Linea Tunnel project, which is still incomplete. The project has been beset by a serious of issues including unexpectedly poor geological conditions, contractors having the wrong kind of insurance, insufficient funds for work to continue and in more recent times, further geological problems. While the Tolima end of the link is now close to completion, work still remains to be done at the Quindio end of the tunnel. Measuring 315m long, the La Gata section is now largely
  • Colombia’s La Linea Tunnel completion in sight
    May 7, 2015
    The completion of Colombia’s long-running La Linea Tunnel project is now in sight, finally. Colombia’s president, Juan Manuel Santos, and vice president, German Vargas Lleras, made a joint announcement that the 8.65km long tunnel will be inaugurated in November 2016. The two tunnel drives (from Quindio and Tolima) have now met in the middle and only lining works are left to be completed. Once the tunnel is operational, it will enable trucks to complete the journey between Cajamarca (Tolima) and Calarca (Qui
  • Colombia continues tunnel plans
    February 17, 2012
    With work on Colombia's first La Linea tunnel still incomplete, discussions are now being held regarding plans for the second tunnel.