Colombia tunnel project conclusion plan

Tendering is commencing for the final portion of works to complete Colombia’s La Linea tunnel project. Around 12% of the work on the tunnel still has to be completed, with the work expected to cost US$68.5 million. The tender is being carried out by Colombia's National Road Institute (Invias). The tunnel project has been delayed for a series of reasons. Colombian contractor Constructora Carlos Collins was constructing the tunnel but did not meet the necessary deadline. As a result, Invias opted to open the
December 6, 2016 Read time: 2 mins
Tendering is commencing for the final portion of works to complete Colombia’s La Linea tunnel project. Around 12% of the work on the tunnel still has to be completed, with the work expected to cost US$68.5 million. The tender is being carried out by Colombia's National Road Institute (2812 Invias). The tunnel project has been delayed for a series of reasons. Colombian contractor Constructora Carlos Collins was constructing the tunnel but did not meet the necessary deadline. As a result, Invias opted to open the tender for the final portion of works required. The project timeline now calls for the tunnel to open to traffic by mid-2018.

When the tunnel finally opens to traffic, it will provide a much safer route for drivers, as well as cutting journey times. The existing road is at a comparatively high altitude and is narrow and twisty with has a poor record for safety, particularly in bad weather. The new tunnel route will offer extra capacity as well as cutting journey times and boosting safety standards.

For more information on companies in this article

Related Content

  • Solution found for Colombian tunnel project?
    March 12, 2015
    A solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover. The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity r
  • Further delays possible for Colombia tunnel
    July 21, 2016
    Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.
  • Colombia’s La Linea Tunnel will be completed
    September 16, 2015
    Colombia's national road institute (Invias) has said that the La Linea tunnel project will open to traffic in 2017. The project has been delayed on several occasions and due to a variety of reasons, presenting a luckless and lengthy tale of woe for Colombia’s transport ministry. Early in its lifetime the project was held back by unexpected geological issues arising from more challenging ground conditions than had been initially realised. The project was also delayed by insurance problems for some of the fir