Colombia connectivity to improve with new bridge

Construction work on Colombia’s landmark Yati-Bodega bridge is already 50% complete. The 2.3km Puente de la Reconciliacion Bridge spans the Magdalena River and when complete, will be the longest in the country. The project is challenging however, due to the river’s flow rate as well as the underlying geology. Once the bridge opens to traffic, it will connect the municipality of Mompox with the rest of Colombia’s Bolivar department. At present Mompox and Magangue are difficult to reach by road due to the lac
February 2, 2017 Read time: 2 mins
Construction work on Colombia’s landmark Yati-Bodega bridge is already 50% complete. The 2.3km Puente de la Reconciliacion Bridge spans the Magdalena River and when complete, will be the longest in the country. The project is challenging however, due to the river’s flow rate as well as the underlying geology. Once the bridge opens to traffic, it will connect the municipality of Mompox with the rest of Colombia’s Bolivar department. At present Mompox and Magangue are difficult to reach by road due to the lack of a direct route. The new bridge will connect Colombia’s important Ruta del Sol and Troncal de Occidente highways. The Puente de la Reconciliacion Bridge is part of a 12km link, which is costing just over US$82 million. The project also includes the construction of the Santa Lucia Bridge and roads linking Isla Grande and Puente Roncador-Bodega. When the bridge is complete it will cut the travel time between Bolivar and central Colombia by four hours.

Progress on the bridge has been good with 18 of its 50 support columns in the river having been already been installed. At the same time 50 of the abutments that will support the bridge’s 224 arches have also been installed. The construction work is being carried out by a consortium, Consorcio Nacional Yati and the bridge itself should be completed by the end of this year, although the connecting roads will take longer to finish.

Related Content

  • New bridge and road projects underway for Chile
    December 18, 2013
    Strong bids have been received for Chile’s Puente Industrial road bridge project, which will be built in Region VIII. Bidders included Spanish firm OHL as well as Besalco Concesiones-Concesiones Viarias Chile Tres and Sacyr Concesiones Chile. Work on the 2.5km bridge is expected to commence in 2014 and the project will cost some US$170 million to construct, with completion expected in 2017. The deal for the four lane bridge includes building access roads and involves a 30 year concession package. The Puente
  • Colombian deals
    February 7, 2012
    The Colombian authorities are agreeing terms with the Colombian electricity transmission company Interconexion Electrica (ISA) for the Autopistas de la Montana highway project. The Bogota-Villavicencio highway was also awarded although other infrastructure projects are still awaiting approval.
  • Further delays possible for Colombia tunnel
    July 21, 2016
    Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
  • Colombia’s massive highway programme is moving forward
    June 13, 2017
    Colombia is pushing ahead with its 4G road development programme. Progress is being made with the construction of the Girardot-Honda-Puerto Salgar road connection, which is expected to cost US$518.6 million and is around 37% complete.