Champlain Bridge set to open by end of year, says SNC-Lavalin

The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
March 6, 2018 Read time: 2 mins
Montreal’s Champlain Bridge: on schedule, so far, with 65% complete and opening set for December (photo courtesy Signature sur le Saint-Laurent Construction S.E.N.C.)
The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project.


Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, will have the six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.
 
The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay bridge with a front span of around 240m and a back span of 120m.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US.

For more information on companies in this article

Related Content

  • Work starting on second Chesapeake Tunnel project
    September 20, 2017
    Work is now starting on a major tunnel project in the US state of Virginia. Construction of a second tunnel connection for the Chesapeake Bay is expected to cost US$756million. The original Chesapeake Bay Tunnel and Bridge crossing opened to traffic in April 1964 and measures just over 37km long. Construction of a second parallel bridge was commenced in 1995 and opened to traffic in 1999. However the central tunnel link was not widened at that time and now carries more traffic than it was designed for, whil
  • Testing time for Tlicho all-season gravel road in Canadian north
    January 27, 2020
    Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
  • Highways England: Lower Thames consultation
    July 14, 2021
    Earlier this year, Highways England announced that the three joint ventures, BFV, Bouygues Murphy and Dragados-Hochtief will be invited to enter into a competitive dialogue.
  • India Bogibeel Bridge project
    December 14, 2016
    Construction work is underway on India’s Bogibeel Bridge, which will span the Brahmaputra River. When complete the bridge is expected to come with a price tag of US$746.8 million. The new bridge will provide both road and rail links over the Brahmaputra River and is expected to open to traffic in March 2018. The novel design features an upper deck with three traffic lanes for road vehicles as well as a lower deck carrying twin rail lines. Measuring 4.9km long, the bridge will be the longest in India carryin