Champlain Bridge set to open by end of year, says SNC-Lavalin

The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
March 6, 2018 Read time: 2 mins
Montreal’s Champlain Bridge: on schedule, so far, with 65% complete and opening set for December (photo courtesy Signature sur le Saint-Laurent Construction S.E.N.C.)
The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project.


Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, will have the six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.
 
The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay bridge with a front span of around 240m and a back span of 120m.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US.

For more information on companies in this article

Related Content

  • Ile-de-France regions sets out highway spending until 2020
    February 6, 2015
    The Isle de France region, essentially the Paris area and extensive surrounding countryside, will spend around €365 million on road infrastructure as part of a five-year transportation plan from this year up to 2020. The overall plan calls for an investment of of €7.3 billion, of which €2.9 billion will come from the central government and €4.4 billion from the Isle de France region. Around EUR €4.5 billion will be used to finance public transport, according to a report by Le Moniteur des Travaux Publics
  • Scotland’s Queensferry Crossing opens to traffic
    August 30, 2017
    The new Queensferry Crossing in Scotland is now open to traffic, with the first vehicles crossing at 2am this morning. The landmark design has set precedents in engineering, its three 207m high towers making it the tallest of its type in the UK and at 2.7km, also the longest three tower cable-stayed bridge built anywhere in the world. The bridge has a design life of 150 years and features two traffic lanes in either direction, as well as emergency lanes on either side. The new bridge will help reduce the ch
  • Scotland’s Queensferry Crossing opens to traffic
    August 30, 2017
    The new Queensferry Crossing in Scotland is now open to traffic, with the first vehicles crossing at 2am this morning. The landmark design has set precedents in engineering, its three 207m high towers making it the tallest of its type in the UK and at 2.7km, also the longest three tower cable-stayed bridge built anywhere in the world. The bridge has a design life of 150 years and features two traffic lanes in either direction, as well as emergency lanes on either side. The new bridge will help reduce the ch
  • Expectations for growth of UAE infrastucture
    February 9, 2012
    The INTERMAT Middle East event is being launched at a pivotal time of major infrastructure development in the region. As with most sectors, the highways industry has not had a fantastic 18 months in the Gulf. Not only has the recession impacted the delivery of projects across the board, GCC Governments' attention have been switching increasingly to rail, as plans to roll out a Gulf-wide rail system gather steam. GCC countries will invest over US$119.6 billion in infrastructure projects over the next decade