Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • Canada: National Bank and Axium refinance Sea-to-Sky Highway
    July 19, 2016
    National Bank Financial and Axium Infrastructure have refinanced the Sea-to-Sky Highway Improvement Project in the Canadian province of British Columbia. A statement from Axium said that the US$427 million 25-year public-private-partnership had “strong investor support and an A2 rating from Moody’s”. The Sea-to-Sky Highway Investment Limited Partnership - Axium Infrastructure, Régime de Rentes du Mouvement Desjardins and Nova Scotia Pension Agency - is the consortium in charge of the concession. In
  • Canada: Ring of Fire road debate heats up
    September 6, 2016
    A 400km road built specifically into the Canada’s isolated but mineral-rich Ring of Fire region could cost between US$204-$443 million, according to a government-funded study. The road, entirely in the province of Ontario, would start in the port of Thunder Bay at the head of the Great Lakes and run northeast to the James Bay area, just south of Hudson Bay.
  • British Columbia decides on Massey Tunnel
    August 20, 2021
    Canada’s Pacific coast province of British Columbia has announced the George Massey Tunnel replacement will be another tunnel and not a bridge as decided earlier.
  • Cold climate binder selection, a tricky business
    May 16, 2017
    Binder selection in cold climates is especially critical for extended pavement life, as Robert Otto Rasmussen, vice president and chief engineer of Transtec Group, explains. The cold climate found in regions such as Canada and the northern regions of the US and Europe poses a particular challenge to engineering a long-lasting, high-quality pavement. Pavements constructed with asphalt in those regions are affected by the asphalt binder’s sensitivity to temperature. Choosing a binder wisely is imperative for