Bridge deck launched for the New Wear Crossing, Sunderland (Video)

March 30, 2017

The 300m bridge deck of Sunderland’s New Wear Crossing has been successfully launched across the river.

The 4,750tonne concrete and steel deck was resting on the south side of the River Wear from where it was inched across to touch the north side in a 20-hour operation. It had to slide through the twin arched towers of the bridge’s double pylon on its way to its final position to connect the city regions of Pallion to the south and Castletown to the north.

The temporary blue steel nose will soon be removed and the remaining 40m section of deck will be built in-situ on the north side this summer.

The project to build the New Wear Crossing started in May 2015 and completion is expected in the spring of 2018. The bridge is phase two of the Sunderland Strategic Transport Corridor, which is a five-phase plan to improve links between the A19 and Sunderland City Centre and the Port of Sunderland.

Scaffolding attached to the top of the pylon will enable cable stays to be fitted, which will be attached to the deck and gradually stressed to take the weight of the bridge later this year. After that, the blue steel temporary towers supporting the deck will be removed and then lighting, road markings and safety features will be added.
Simon Fryer, a technical director of Buro Happold Engineering, who led the team that designed the bridge, said it’s been three years of hard but exciting work.

UK-based 1622 Farrans Construction and Belgian bridge specialist Victor Buck Steel Construction formed a partnership to create the FVB Joint Venture, main contractor for the bridge. FVB JV’s design team is led by Buro Happold Engineering and Roughan & O'Donovan, as well as independent checker 6801 Ramboll.

Victor Buyck Steel spent a year fabricating the pylon at its canal-side yard in Ghent. Because of its size, 8569 Sarens, a global heavy lifting and engineering transport specialist, was called in to gingerly shift the completed pylon onto two canal barges for transport along the canal to the sea port. Sarens transferred the pylon onto one, larger 100m-long seagoing barge.

When the pylon arrived about 1.5km off the coast at Sunderland, it was met by harbour tugs which brought it into port. On a specific high tide, it was carefully towed about 4.5km upriver to the site of the cofferdam between Pallion and Castletown.

The New Wear Crossing is the first bridge to be built over the River Wear in Sunderland for more than 40 years. World Highways recently featured the work as a <%$Linker:

2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 29953 0 oLinkExternal key project report Visit Key Project Report page false /categories/road-highway-structures/features/sunderlands-new-wear-crossing-takes-shape/ false false%> in the magazine and on the website.

For more information on companies in this article

Related Content

  • Duisburg double for lift specialist Sarens
    June 5, 2024
    Heavy lift specialist Sarens overcame challenging wind and water conditions during installation of two strategic road bridges - the Oberbürgermeister Karl Lehr Brücke and the Hafenkanalbrücke - in the German city of Duisburg.
  • Tees Valley crossing project consultation nears an end
    May 9, 2019
    Public consultation is nearly closed for a possible new crossing across the River Tees in northern England that could cost upwards of €350 million. A €230-290 million Tees Viaduct Capacity Enhancement project is the preferred option against a €350 million Tees Viaduct option, according to the recently created Tees Valley Combined Authority, the local government. Capacity Enhancement project would see a two-lane bridge built parallel to the existing A19 viaduct to carry traffic travelling northbound an
  • North Viaduct completed on UK’s Mersey Gateway bridge project
    April 19, 2017
    Concrete finishing work has started on the completed north approach viaduct of England’s new 2.13km Mersey Gateway project. Over the past three years, around 18,400m³of concrete was used to build the viaduct. When complete near the end of this year, around 60,000 vehicles are expected to use the toll bridge every day, or nearly 22 million vehicles annually.
  • Canadian PM Trudeau warned of costs rises for Gordie Howe Bridge
    January 11, 2016
    A devaluing Canadian dollar has pushed up the cost for building a signature Windsor-Detroit bridge by around US$2.5 billion, according to Canadian media reports. The increase more than doubles what was believed needed by the Canadian government to construct the Gordie Howe Bridge, named after a Canadian ice hockey player who played most of his career for the Detroit Red Wings. The toll bridge, to be built under a public private partnership, will link the US city of Detroit, in the state of Michigan, w