North Viaduct completed on UK’s Mersey Gateway bridge project

Concrete finishing work has started on the completed north approach viaduct of England’s new 2.13km Mersey Gateway project. Over the past three years, around 18,400m³of concrete was used to build the viaduct. When complete near the end of this year, around 60,000 vehicles are expected to use the toll bridge every day, or nearly 22 million vehicles annually.
April 19, 2017 Read time: 3 mins

Concrete finishing work has started on the completed north approach viaduct of England’s new 2.13km 6126 Mersey Gateway project.


Over the past three years, around 18,400m³of concrete was used to build the viaduct. When complete near the end of this year, around 60,000 vehicles are expected to use the toll bridge every day, or nearly 22 million vehicles annually.

Finishing work on the north viaduct involves water-proofing the deck, installing fascias along its sides and laying a road surface, said Hugh O’Connor, general manager for Merseylink Construction Joint Venture.

A range of specialist equipment was used to build the north approach viaduct, including the 280tonne wing-traveller machine used to build the outer road lanes on either side of the north approach viaduct. It followed Trinity, the 1,700tonne 157m-long movable scaffold system -MSS - which was used to build the central part of the carriageway.

Structural work continues on the south approach viaduct, which is expected to be finished this summer. Once complete, the two elevated approach roads will stretch across the saltmarsh on either side of the River Mersey, connecting the new bridge to the main road networks in the towns of Runcorn and Widnes.

Last month, construction of the bridge deck and stay cables also passed the halfway point.
 
The 2.13km Mersey Gateway Project, one of the largest infrastructure initiatives in the UK, is one of the government’s top 40 priority projects in the National Infrastructure Plan. The 1km-long six-lane bridge will consist of four spans supported from three towers in the estuary of the River Mersey near Liverpool. The 80m-high central tower will be shorter than the two outer towers, at 110m and 125m in height.

The <%$Linker:

2

External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal Merseylink Consortium false http://www.merseygateway.co.uk/ false false%> was appointed by Halton Borough Council as the project company in 2014 on a 30-year contract to design, build, finance and operate the structure. The construction joint venture is made up of Kier Infrastructure and Overseas, 1026 Samsung C&amp;T and 1340 FCC Construcci&#243;n. Equity partners are 2378 Macquarie Capital Group, BBGI and FCC Construcción.
 
Emovis will deliver and operate tolling for the consortium through its <%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal merseyflow brand false http://www.merseyflow.co.uk/ false false%>.

 

For more information on companies in this article

Related Content

  • UK: Work starts on Mersey Gateway main bridge deck
    June 2, 2016
    Work has started on 2.2km Mersey Gateway’s main bridge deck as the project enters its third year of construction. The new six-lane toll bridge will link the English towns of Runcorn and Widnes and teams will begin to connect the steel support cables to the deck and upper pylons this summer. Trinity, the project’s movable scaffolding system (MSS), has cast the first 250m of the north approach viaduct and a new MSS is on its way to Halton to build the south approach viaduct. The local road network is al
  • First bridge deck section joined on UK’s Mersey Gateway project
    June 30, 2017
    The Mersey Gateway bridge project near Liverpool in England passed a milestone recently with the first joining of two of the deck sections.
  • First deck span completed for Mersey Gateway's north approach viaduct
    February 12, 2016
    The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
  • Mersey Gateway shortlisted for the UK’s CIEEM ecology award
    June 1, 2017
    The team building the Mersey Gateway bridge has reached the final of a UK national competition that recognises excellence in ecology and environmental management. The project team entered this year’s Chartered Institute of Ecology and Environmental Management (CIEEM) Best Practice awards. The winners highlight outstanding examples of environmental management on large-scale projects.