Concrete finishing work has started on the completed north approach viaduct of England’s new 2.13km Mersey Gateway project. Over the past three years, around 18,400m³of concrete was used to build the viaduct. When complete near the end of this year, around 60,000 vehicles are expected to use the toll bridge every day, or nearly 22 million vehicles annually.
April 19, 2017 Read time: 3 mins

Concrete finishing work has started on the completed north approach viaduct of England’s new 2.13km 6126 Mersey Gateway project.


Over the past three years, around 18,400m³of concrete was used to build the viaduct. When complete near the end of this year, around 60,000 vehicles are expected to use the toll bridge every day, or nearly 22 million vehicles annually.

Finishing work on the north viaduct involves water-proofing the deck, installing fascias along its sides and laying a road surface, said Hugh O’Connor, general manager for Merseylink Construction Joint Venture.

A range of specialist equipment was used to build the north approach viaduct, including the 280tonne wing-traveller machine used to build the outer road lanes on either side of the north approach viaduct. It followed Trinity, the 1,700tonne 157m-long movable scaffold system -MSS - which was used to build the central part of the carriageway.

Structural work continues on the south approach viaduct, which is expected to be finished this summer. Once complete, the two elevated approach roads will stretch across the saltmarsh on either side of the River Mersey, connecting the new bridge to the main road networks in the towns of Runcorn and Widnes.

Last month, construction of the bridge deck and stay cables also passed the halfway point.
 
The 2.13km Mersey Gateway Project, one of the largest infrastructure initiatives in the UK, is one of the government’s top 40 priority projects in the National Infrastructure Plan. The 1km-long six-lane bridge will consist of four spans supported from three towers in the estuary of the River Mersey near Liverpool. The 80m-high central tower will be shorter than the two outer towers, at 110m and 125m in height.

The <%$Linker:

2

External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal Merseylink Consortium false http://www.merseygateway.co.uk/ false false%> was appointed by Halton Borough Council as the project company in 2014 on a 30-year contract to design, build, finance and operate the structure. The construction joint venture is made up of Kier Infrastructure and Overseas, 1026 Samsung C&amp;T and 1340 FCC Construcci&#243;n. Equity partners are 2378 Macquarie Capital Group, BBGI and FCC Construcción.
 
Emovis will deliver and operate tolling for the consortium through its <%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal merseyflow brand false http://www.merseyflow.co.uk/ false false%>.

 

For more information on companies in this article

Related Content

  • New Mersey gateway bridge project underway
    September 23, 2015
    Work is starting on the approach viaducts for the new Mersey Gateway Bridge in the UK. The project is using longest bridge-building machine in Europe, which was named during a ceremony to mark the latest key stage the Mersey Gateway Project. Most machines of this kind can only build bridge spans of up to 60m. However, the MSS for the Mersey Gateway Bridge was specially made so it is able to cast spans of up to 70m.
  • Second giant moveable scaffolding system set for Mersey Gateway
    May 4, 2016
    A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the Mersey Gateway Project, a toll bridge over the Mersey River in England. The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.
  • Emovis continues with Mersey Gateway tolling
    March 18, 2022
    Emovis provides collection of tolls and charges for both Mersey Gateway Crossing and the older 87m-long Silver Jubilee Bridge through its merseyflow brand name.
  • The Mersey Gateway bridge project continues on schedule
    October 18, 2016
    Work continues on the 2.3km Mersey Gateway signature bridge project close to Liverpool in the UK. David Arminas reports on some of the construction highlights. Under construction is a cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool. Including the approach viaducts on each side, it will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will b