Tees Valley crossing project consultation nears an end

Public consultation is nearly closed for a possible new crossing across the River Tees in northern England that could cost upwards of €350 million. A €230-290 million Tees Viaduct Capacity Enhancement project is the preferred option against a €350 million Tees Viaduct option, according to the recently created Tees Valley Combined Authority, the local government. Capacity Enhancement project would see a two-lane bridge built parallel to the existing A19 viaduct to carry traffic travelling northbound an
May 9, 2019 Read time: 2 mins
Artist’s impression of the New Tees Crossing Tees Viaduct Capacity Enhancement option

Public consultation is nearly closed for a possible %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external new crossing across the River Tees false https://teesvalley-ca.gov.uk/transport/new-tees-crossing-consultation/ false false%> in northern England that could cost upwards of €350 million.

A €230-290 million Tees Viaduct Capacity Enhancement project is the preferred option against a €350 million Tees Viaduct option, according to the recently created Tees Valley Combined Authority, the local government.

Capacity Enhancement project would see a two-lane bridge built parallel to the existing A19 viaduct to carry traffic travelling northbound and the existing structure widened to allow for an extra lane of southbound traffic.

The Tees Viaduct option would be to construct a four-lane bridge parallel to the existing A19 viaduct to handle both north and southbound traffic.

The chosen option will be announced in autumn with confirmation of central government funding soon after. Construction is set for 2023-27.

The Tees Valley Combined Authority was created in April 2016, combining Darlington, Hartlepool, Middlesbrough, Redcar & Cleveland and Stockton-on-Tees. In 2017, residents elected a mayor whose responsibilities include transport, business growth and investment.

The existing 2.9km-long viaduct, opened in 1975, is a girder bridge with reinforced concrete piers and pier bends supporting steel-plate girder beams and a composite deck with around 200 moving parts. Distance between the abutments is 1.95km and none of the piers are in the river. It has 68 spans on the main north south route, with the largest span, 117m, being over the river.

In 1989 work finished on enclosing the underside of the bridge with steel and glass-reinforced plastic panelling to protect the primary structure from weathering and to allow safer and more easy maintenance.

Related Content

  • Second Tees Valley Viaduct proposed at Middlesbrough
    March 19, 2019
    Proposals for a second crossing over the Tees River in northern England have gone out to public consultation, according to media reports. The Tees Valley Combined Authority, the local authority, said there are two options to take the A19 trunk road over the River Tees at the city of Middlesbrough. One plan, costing between €235-292 million, would be for a bridge parallel to the existing one where each bridge would traffic in only one directions. The other option is for a four-lane €350 million brid
  • Second giant moveable scaffolding system set for Mersey Gateway
    May 4, 2016
    A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the Mersey Gateway Project, a toll bridge over the Mersey River in England. The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.
  • Delay to SF-Oakland Bay Bridge East Span opening and probe report
    July 9, 2013
    The Toll Bridge Program Oversight Committee (TBPOC) today said that the previously scheduled Labor Day (2 Sep) opening of the new East Span of the San Francisco-Oakland Bay Bridge has been postponed. News of the delayed opening was announced at the same time as TBPOC released its investigative report into the 32 bolts that broke on the Bay Bridge in March 2013, and its review of other bolts on the bridge. The contractor now forecasts that the steel saddle retrofit of the failed bolts on the east pier will b
  • Systra, Kiewit and Hatch to build third bridge in Kingston, Canada
    August 31, 2018
    Kingston, Canada, has selected Systra International Bridge Technologies, Peter Kiewit Sons and Hatch as the preferred consortium for the design and build Third Crossing project. Seven international teams answered the requests for proposals in February and 2018 with Systra, Kiewit and Hatch eventually chosen from a shortlist of three groups. The consortium will use an integrated project delivery model for the two-lane 1.2km bridge with a pedestrian and cycle path over the Cataraqui River will connect