Romania set to start Sebes-Turda motorwa construction

Construction of the proposed Sebes-Turda motorway will start by the end of November, according to Eugen Cecan, director of Romania’s Regional Administration for Roads and Bridges. Cecan made the announcement in Cluj, the second most populous city in Romania after the capital Bucharest and considered the unofficial capital to the historic province of Transylvania. Cost of the 70km project is around US$500.34 million (€400 million), with 85% coming from the European Union as grants and the central gover
November 7, 2014 Read time: 2 mins
Construction of the proposed Sebes-Turda motorway will start by the end of November, according to Eugen Cecan, director of Romania’s Regional Administration for Roads and Bridges.

Cecan made the announcement in Cluj, the second most populous city in Romania after the capital Bucharest and considered the unofficial capital to the historic province of Transylvania.

Cost of the 70km project is around US$500.34 million (€400 million), with 85% coming from the 1116 European Union as grants and the central government investing the remaining 15%.

Cecan said the motorway will be completed by March 2016 and run north from Sebes, with a population of around 25,000, to Turda with a population of 45,000.

Sebes is at the crossroads of two main highways in Romania: E68 European route - DN1 coming from Sibiu and going towards Deva and E81 European route - DN7 coming from Sibiu and going towards Alba-Iulia and Cluj.

Construction work on the motorway is split into four contracts, awarded last year.

Lot 1 – 17km from the highway entrance near the interchange with the A1 motorway at Sebeș to Paraul Iovului – was awarded to the Italian consortium 7809 Salini Impregilo at a cost of nearly $151 million (539,488,704 lei).

Lot 2, around 24km from Paraul Iovului to Aiud, was awarded to an Italian-Romanian consortium that includes RCM Costruzioni, Shelter Construct and Eurocerad International for nearly $128.5 million (460,019,270 lei).

The 12.5km Lot 3 section from Aiud to the Decea interchange is being built by the consortium of Tirrena Scavi and Societa Italiana per Condotte d'Acqua at a cost of cost of $117.5 million (420,511,921 lei).

Lot 4, around 16km from the Decea interchange to the interchange with the A3 motorway near Turda, was awarded to the Romanian division of 3976 Porr Group, Porr Construct SRL, German division Porr Bau, for a cost of $131.4 million (470,004,894 lei).

For more information on companies in this article

Related Content

  • Land acquisition delays the start of Bratislava's orbital road
    September 25, 2017
    Land acquisition issues have stalled the start of construction of Bratislava’s orbital road by up to eight months. Work could begin this autumn, according to a report by the Slovak Spectator, because the government is working on laws that would allow construction before all land is acquired.
  • Lane, part of Salini Impregilo Group, wins I-440/US 1 deal in North Carolina
    October 26, 2018
    Lane Construction, the US subsidiary of Italy’s Salini Impregilo Group, has won a US$346 million design-build contract for the Interstate I-440/US 1 in North Carolina. Lane will be making improvements to the Interstate I-440/US 1 Wake County from south of Walnut Street to north of Wade Avenue. Around 10.5km of the highway - referred to locally as the Raleigh Beltline - will be widened from four lanes to six lanes. The work involves replacing pavement and bridges and upgrading interchanges and is expected
  • Spedition UMB and Tehnostrade to build an orbital around Bacau
    August 14, 2018
    A joint venture of Spedition UMB and Tehnostrade has won the design-build contract for an orbital road around the Romanian city of Bacau. Romania’s National Company for the Administration of Road Infrastructure (CNAIR) awarded the contract that is expected to be worth almost €145 million. Planning is expected to last six months and construction to take 30 months for the nearly 31km road of which around 16km will be motorway. The road around Bacau, with a population of more than 200,000, will be integr
  • Lane picks up Florida SR408 widening project in Orange County
    July 18, 2017
    Lane Construction Corporation has won a US$76 million contract to widen a section of State Road 408 in Orange County, Florida.The project entails adding a thirds lane to each carriageway over a 5.2km stretch of SR408. It will also involve widening a ramp from two lanes to three lanes, adding sound walls as well as extra open road tolling - ORT - lanes.