Land acquisition delays the start of Bratislava's orbital road

Land acquisition issues have stalled the start of construction of Bratislava’s orbital road by up to eight months. Work could begin this autumn, according to a report by the Slovak Spectator, because the government is working on laws that would allow construction before all land is acquired.
September 25, 2017 Read time: 2 mins

Land acquisition issues have stalled the start of construction of Bratislava’s orbital road by up to eight months.

Work could begin this autumn, according to a report by the Slovak Spectator, because the government is working on laws that would allow construction before all land is acquired.

Construction was supposed to start last year on the €1.8 billion project contracted under a public-private-partnership to the consortium of Obchvat Nula of 930 Cintra, Australia-based infrastructure investor 2378 Macquarie Capital and Austrian construction contractor 3976 PORR. The design, build, finance, operate and maintain contract is for 34 years, with the first four years to be construction.

The deal is the first in Slovakia for Cintra, a 2717 Ferrovial Agroman subsibiary. The project will create the D4 ring road between Jarovce and Raca around Bratislava as well as a new radial road, the R7.

According to Ferrovial, the new 27km D4 will have two lanes in each direction and will create a beltway to the east of the city and a connection with existing radial roads. The 32km R7 radial highway, between Prievoz and Holice, will have two to three lanes each way, running in a south-easterly direction from the city centre.
 
Cintra will develop this project, while design and construction will be carried out by a joint venture headed by Ferrovial Agroman with Porr. Operation and maintenance will be handled by the concession company.

Under the concession model, the design and construction joint venture is formed by Ferrovial Agroman and PORR.

The concession-holder is Cintra, Macquarie Capital and PORR. Cintra’s assets include the 407 ETR highway in Canada, the North Tarrant Express in the US and Ausol in Spain.

Meanwhile, two highway projects are nearing the tender stage, likely by the end of the year. These are the 4.3km section of the R4 Presov bypass, costing likely around €192 million, and the 13.5km section of the R2 between Mytna and Lovinobane, cost of which has yet to be calculated.

For more information on companies in this article

Related Content

  • Slovakia: D4/R7 Bratislava bypass work to start early this year
    January 10, 2017
    Construction will start early this year on 59km of highway as part of the D4/R7 bypass of the Slovakian capital Bratislava. Ferrovial through its subsidiaries Cintra Infraestructuras and Ferrovial Agroman is leading the consortium on the public-private partnerships deal worth around €1.9 billion, according to media reports. Ferrovial reached financial close on the project in June, noting that their investment would be around €975 million. The first stage of the design, build, financing, operate and ma
  • Slovakia’s D4/R7 zero bypass of Bratislava picks up award
    February 10, 2017
    Slovakia’s D4/R7 zero bypass of Bratislava has picked up the Best Transaction in Europe award given by the UK magazine Project Finance International. The Ministry of Transport and Construction received the award in London in early February. The ministry said that the contract is notable for being the first whereby a project had combined funding from European Union investment and structural funds and the EU fund for strategic investment. World Highways reported in January that construction will start early
  • Slovakia’s Cabinet to have final say on D4 Bratislava bypass
    February 9, 2016
    The government of Robert Fico has said it will decide the fate of the controversial €1 billion Bratislava bypass, the D4 motorway project, possibly ahead of a national parliamentary election next month. Fico, who also was prime minister from 2006-2010, was re-appointed after leading his Direction Social Democracy party (SMER-SD) to a landslide victory in the 2012 parliamentary election. His party won 83 seats and formed an absolute majority government, Slovakia’s first since 1989. Controversy continue
  • Slovakia: early 2017 restart for work on the Cebrat Tunnel
    May 27, 2016
    Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn