Romania set to start Sebes-Turda motorwa construction

Construction of the proposed Sebes-Turda motorway will start by the end of November, according to Eugen Cecan, director of Romania’s Regional Administration for Roads and Bridges. Cecan made the announcement in Cluj, the second most populous city in Romania after the capital Bucharest and considered the unofficial capital to the historic province of Transylvania. Cost of the 70km project is around US$500.34 million (€400 million), with 85% coming from the European Union as grants and the central gover
November 7, 2014 Read time: 2 mins
Construction of the proposed Sebes-Turda motorway will start by the end of November, according to Eugen Cecan, director of Romania’s Regional Administration for Roads and Bridges.

Cecan made the announcement in Cluj, the second most populous city in Romania after the capital Bucharest and considered the unofficial capital to the historic province of Transylvania.

Cost of the 70km project is around US$500.34 million (€400 million), with 85% coming from the 1116 European Union as grants and the central government investing the remaining 15%.

Cecan said the motorway will be completed by March 2016 and run north from Sebes, with a population of around 25,000, to Turda with a population of 45,000.

Sebes is at the crossroads of two main highways in Romania: E68 European route - DN1 coming from Sibiu and going towards Deva and E81 European route - DN7 coming from Sibiu and going towards Alba-Iulia and Cluj.

Construction work on the motorway is split into four contracts, awarded last year.

Lot 1 – 17km from the highway entrance near the interchange with the A1 motorway at Sebeș to Paraul Iovului – was awarded to the Italian consortium 7809 Salini Impregilo at a cost of nearly $151 million (539,488,704 lei).

Lot 2, around 24km from Paraul Iovului to Aiud, was awarded to an Italian-Romanian consortium that includes RCM Costruzioni, Shelter Construct and Eurocerad International for nearly $128.5 million (460,019,270 lei).

The 12.5km Lot 3 section from Aiud to the Decea interchange is being built by the consortium of Tirrena Scavi and Societa Italiana per Condotte d'Acqua at a cost of cost of $117.5 million (420,511,921 lei).

Lot 4, around 16km from the Decea interchange to the interchange with the A3 motorway near Turda, was awarded to the Romanian division of 3976 Porr Group, Porr Construct SRL, German division Porr Bau, for a cost of $131.4 million (470,004,894 lei).

For more information on companies in this article

Related Content

  • Romania eyes PPP for three projects, including the Rasnov-Ploiesti
    June 4, 2018
    The Government of Romania will build three motorway segments through a public-private partnership. The motorway segments in question are the 109km long Ungheni-Iasi-Targu Neamt segment, which will have a bridge built over the river Prut, the 100km long Rasnov-Brasov-Ploiesti motorway section, and the 550km long motorway segment between Alexandria and Lugoj.
  • Budimex consortium win Poland’s Ostroda ringroad court case
    March 18, 2015
    A district court in the Polish town of Olsztyn has ruled in favour of a consortium of Budimex and Ferrovial Agroman which challenged the awarding of a ringroad contract to a rival. The ruling means that the Salini consortium’s winning bid for the construction of a ringroad around Ostroda is overturned on the basis that it was ineffectually low. This means that the contract will go to the Budimex consortium which proposed to build the road for around €223 million. Polish builder Budimex is the consortium's m
  • Wide variations in Europe's road safety figures
    May 14, 2012
    Road safety in Romania continues to be a major issue, with the country seeing more deaths in 2009 than in 2001. A study by the European Transport Safety Council (ETSC) shows that Romanian roads are eight times more dangerous than similar links in Sweden, which has Europe’s best record for road safety (see also Safety Report). Romania, along with Malta, has bucked a trend within Europe of reducing road accidents levels between 2001 and 2009 according to the report. However, while Malta’s road fatality rate
  • Romanian road bids
    February 29, 2012
    Bidding is healthy for key road projects in Romania. Four companies and one consortium have submitted bids for the modernisation of the DN18 national road linking Baia Mare with Iacobeni.