Mersey Gateway: Consortia Talks

The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli
April 4, 2012 Read time: 3 mins
RSSThe competitive dialogue phase of the Mersey Gateway Project has begun.

The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months.

The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013.

The value of the construction phase of the project, including land, is estimated at US$961million.

Councillor Rob Polhill, Leader of Halton Borough Council, said: “The rest of this year will be critical in shaping the final detail of the bidders’ proposals, and we will be working closely with each bidding group to ensure that we are able to maintain quality on this project whilst continuing to deliver value for money for the public purse.”

Steve Nicholson, Mersey Gateway Project (MGP) director, said: “The quality of the initial submissions was excellent, and I am looking forward to working with each of the bidding groups to enable them to pull together their detailed proposals.”

Last month Halton Borough Council announced the identities of the three shortlisted bidders. They are:

1146 Balfour Beatty, 979 Bouygues Travaux Publics, 2376 EGIS Projects consortium, comprising equity members Balfour Beatty plc, Bouygues Travaux Publics and Egis Projects.

Merseylink consortium, comprising equity members 2378 Macquarie Capital Group Limited, 2516 Bilfinger and Berger Project Investments Limited, Vialia Sociedad Gestora de Concesiones de Infraestructuras S.L. and 1340 FCC Construcción S.A.

MGL consortium, comprising equity members 3932 Galliford Try Investments Limited, 981 Hochtief PPP Solutions GmbH and 3933 Iridium Concesiones de Infraestructuras S.A.

The centrepiece of the MGP is a new six-lane toll bridge over the Mersey between the towns of Runcorn and Widnes.

In addition to speeding up journey times and improving journey reliability in the region, it is intended to act as a catalyst for investment and bring benefits over four times greater than the investment cost.

The benefits are predicted to include the creation of an estimated 4,640 new jobs through direct employment, regeneration activity and inward investment, and the generation of a conservative estimate of $99million a year in Gross Value Added from the new jobs by 2030.

The existing Silver Jubilee Bridge will also be tolled as part of the project.

It is anticipated that construction work will start within two years, and that the new bridge will take around three years to complete.

As well as the income from tolls, the 5432 Department for Transport will provide $138million in capital grant towards land and remediation and up to $23.3million per year in long-term revenue support for 26.5 years from opening to fund the scheme.

For more information on companies in this article

Related Content

  • FCC and ACS of Spain to take part in tender for UK’s Mersey bridge project
    May 22, 2013
    Spanish construction companies FCC and ACS say they will take part in the tender of the US$3.05 billion (£2bn) Mersey bridge project in the UK. FCC and ACS will take part as members of two of the three consortia that have expressed an interest. FCC will take part in the tender through its German subsidiary Hochtief, and it infrastructures division Iridium, within the consortium led by BAM Nuttal of the UK. Meanwhile, ACS will be part of the Bilfinger and Macquarie consortium through its subsidiary Globalvia
  • First bridge deck section joined on UK’s Mersey Gateway project
    June 30, 2017
    The Mersey Gateway bridge project near Liverpool in England passed a milestone recently with the first joining of two of the deck sections.
  • North Viaduct completed on UK’s Mersey Gateway bridge project
    April 19, 2017
    Concrete finishing work has started on the completed north approach viaduct of England’s new 2.13km Mersey Gateway project. Over the past three years, around 18,400m³of concrete was used to build the viaduct. When complete near the end of this year, around 60,000 vehicles are expected to use the toll bridge every day, or nearly 22 million vehicles annually.
  • UK: Work starts on Mersey Gateway main bridge deck
    June 2, 2016
    Work has started on 2.2km Mersey Gateway’s main bridge deck as the project enters its third year of construction. The new six-lane toll bridge will link the English towns of Runcorn and Widnes and teams will begin to connect the steel support cables to the deck and upper pylons this summer. Trinity, the project’s movable scaffolding system (MSS), has cast the first 250m of the north approach viaduct and a new MSS is on its way to Halton to build the south approach viaduct. The local road network is al