Skip to main content

Mersey Gateway: Consortia Talks

The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli
April 4, 2012 Read time: 3 mins
RSSThe competitive dialogue phase of the Mersey Gateway Project has begun.

The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months.

The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013.

The value of the construction phase of the project, including land, is estimated at US$961million.

Councillor Rob Polhill, Leader of Halton Borough Council, said: “The rest of this year will be critical in shaping the final detail of the bidders’ proposals, and we will be working closely with each bidding group to ensure that we are able to maintain quality on this project whilst continuing to deliver value for money for the public purse.”

Steve Nicholson, Mersey Gateway Project (MGP) director, said: “The quality of the initial submissions was excellent, and I am looking forward to working with each of the bidding groups to enable them to pull together their detailed proposals.”

Last month Halton Borough Council announced the identities of the three shortlisted bidders. They are:

1146 Balfour Beatty, 979 Bouygues Travaux Publics, 2376 EGIS Projects consortium, comprising equity members Balfour Beatty plc, Bouygues Travaux Publics and Egis Projects.

Merseylink consortium, comprising equity members 2378 Macquarie Capital Group Limited, 2516 Bilfinger and Berger Project Investments Limited, Vialia Sociedad Gestora de Concesiones de Infraestructuras S.L. and 1340 FCC Construcción S.A.

MGL consortium, comprising equity members 3932 Galliford Try Investments Limited, 981 Hochtief PPP Solutions GmbH and 3933 Iridium Concesiones de Infraestructuras S.A.

The centrepiece of the MGP is a new six-lane toll bridge over the Mersey between the towns of Runcorn and Widnes.

In addition to speeding up journey times and improving journey reliability in the region, it is intended to act as a catalyst for investment and bring benefits over four times greater than the investment cost.

The benefits are predicted to include the creation of an estimated 4,640 new jobs through direct employment, regeneration activity and inward investment, and the generation of a conservative estimate of $99million a year in Gross Value Added from the new jobs by 2030.

The existing Silver Jubilee Bridge will also be tolled as part of the project.

It is anticipated that construction work will start within two years, and that the new bridge will take around three years to complete.

As well as the income from tolls, the 5432 Department for Transport will provide $138million in capital grant towards land and remediation and up to $23.3million per year in long-term revenue support for 26.5 years from opening to fund the scheme.

For more information on companies in this article

Related Content

  • Mersey Gateway shortlisted for the UK’s CIEEM ecology award
    June 1, 2017
    The team building the Mersey Gateway bridge has reached the final of a UK national competition that recognises excellence in ecology and environmental management. The project team entered this year’s Chartered Institute of Ecology and Environmental Management (CIEEM) Best Practice awards. The winners highlight outstanding examples of environmental management on large-scale projects.
  • Key route upgrades for Scotland
    July 19, 2012
    Major road projects in Scotland will improve the country’s transport connections. Plans are now in hand to fast-track the project to convert the A9 to dual carriageway status along its entire length. The road is a major transport artery to the north of Scotland, connecting the Central Belt in the south with the northern city of Inverness, providing the main gateway to the north of the country. The plans call for the upgrading of the A9 to dual carriageway status between Perth and Inverness. Work on the 5km
  • Emovis continues with Mersey Gateway tolling
    March 18, 2022
    Emovis provides collection of tolls and charges for both Mersey Gateway Crossing and the older 87m-long Silver Jubilee Bridge through its merseyflow brand name.
  • First stay cable installed on UK’s Mersey Gateway bridge
    October 31, 2016
    The first stay cable, 52m long, connecting the Mersey Gateway south pylon to the main bridge deck, has been installed on the Mersey Gateway Project.