48 hours re-opening

Using demolition tools from Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.
July 6, 2012 Read time: 2 mins
Using Atlas Copco demolition attachments helped the fast removal of an old bridge over a busy German autobahn in a strict timeframe
Using demolition tools from 161 Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.

Near Randersacker an old bridge crossing the river Main built in 1964 was demolished using explosives and a new wider one was erected just 3m away. This new bridge is already in use.

After the 540m long Main bridge was blown up, the B13 underneath the bridge was to be re-opened to traffic in just 48 hours. This required some 1,500m3 of reinforced concrete which collapsed on this particular section of the B13 to be crushed and another 800m3 of a layer provided to protect the top surface of the road to be removed. Across the entire length of the former pre-stressed steel bridge, a total of 25,000m3 of reinforced concrete had to be taken care of.

Eight Atlas Copco hydraulic breakers with service weights from 1.2-7tonnes were used for the job by the contractor Ruppert KG Erdbau + Abbruch while six hydraulic pulverisers were used to crush the bridge fragments on the spot. Part of the bridge could not be demolished using explosives and was instead cut down using Atlas Copco CC 2500 U and CC 3300 U CombiCutters mounted on 718 Liebherr R954 and R974 long reach excavators. The B13 was already cleared after just 36 hours, so that the Federal road could be opened to traffic much earlier than scheduled.

For more information on companies in this article

Related Content

  • Cost-saving compact twin layer asphalt paving
    February 28, 2012
    Twin-layer paving offers high quality, long lasting road surfaces to be constructed. Paver manufacturer Dynapac is one of the pioneers of the twin-layer paving technique, which it calls Compactasphalt. According to Dynapac this method offers major benefits to contractors and clients alike as roads surfaced using this technique last longer and are cheaper to maintain. To ensure contractors have maximum utilisation of their machines, Dynapac offers a modular paver system that can be operated using the convent
  • Kentucky’s 1931 Ledbetter road Bridge comes to an explosive end
    October 1, 2014
    Specialist demolition contractors working for the Kentucky Transportation Cabinet have successfully brought down one truss span of the Old Ledbetter Bridge near Paducah. The bridge has been taking traffic across the Mississippi River since 1931. Boat traffic on the Tennessee River was halted for about 90 minutes by the U.S. Coast Guard. KYTC said there were several audible warning signals, then a countdown, followed by a flash and puff of smoke from the explosive charges. As sound of the explosion echoed a
  • Environmentally friendly demolition of famous US Bay Bridge to take years
    March 18, 2013
    While the new eastern span of northern California’s Bay Bridge between San Francisco and Oakland will open to traffic this September, the task of taking down the old eastern bridge span roadway is likely to take years. Speaking to a local TV station Brad McCrea, regulatory director of the Bay Conservation and Development Commission, the state agency that oversees protection of the Bay Area, said: “Taking the old Bay Bridge [eastern span roadway] down is as practically as big a project as putting the new one
  • Testing high performance road markings
    February 9, 2012
    High performance markings are among the safety products used to guide traffic safely, but they must be tested and checked. Patrick Smith reports. Road construction zones, zebra crossings, tunnels and areas with frequent fog are particular focal points with regard to road user safety. This is why manufacturers, authorities and contractors are always eager to use innovative road markings and special studs or, where necessary, lane control devices to assist both drivers and pedestrians in all conditions, parti