48 hours re-opening

Using demolition tools from Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.
July 6, 2012 Read time: 2 mins
Using Atlas Copco demolition attachments helped the fast removal of an old bridge over a busy German autobahn in a strict timeframe
Using demolition tools from 161 Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.

Near Randersacker an old bridge crossing the river Main built in 1964 was demolished using explosives and a new wider one was erected just 3m away. This new bridge is already in use.

After the 540m long Main bridge was blown up, the B13 underneath the bridge was to be re-opened to traffic in just 48 hours. This required some 1,500m3 of reinforced concrete which collapsed on this particular section of the B13 to be crushed and another 800m3 of a layer provided to protect the top surface of the road to be removed. Across the entire length of the former pre-stressed steel bridge, a total of 25,000m3 of reinforced concrete had to be taken care of.

Eight Atlas Copco hydraulic breakers with service weights from 1.2-7tonnes were used for the job by the contractor Ruppert KG Erdbau + Abbruch while six hydraulic pulverisers were used to crush the bridge fragments on the spot. Part of the bridge could not be demolished using explosives and was instead cut down using Atlas Copco CC 2500 U and CC 3300 U CombiCutters mounted on 718 Liebherr R954 and R974 long reach excavators. The B13 was already cleared after just 36 hours, so that the Federal road could be opened to traffic much earlier than scheduled.

For more information on companies in this article

Related Content

  • Cleveland Bridge is all decked out on the England’s A14 scheme
    June 4, 2019
    As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
  • Speed and precision make for perfect tunnelling combination
    May 21, 2014
    Speed and precision have been the hallmarks of a number of major road tunnelling projects across the globe over the last 12 months, as the latest sector equipment from leading manufacturers has found itself in high demand. Guy Woodford reports Herrenknecht tunnel boring machines (TBM) have been busy tunnelling under major Chinese rivers, demonstrating phenomenal speed, top safety levels and extreme precision while playing a key role in the construction of road tunnels in the Yangtze River Delta. The Yang
  • Liebherr piling machines on Vietnam road project
    March 7, 2018
    Crucial piling work for the elevated approach to a bridge at Haiphong in Vietnam has been carried out by a Liebherr rig Highly productive and reliable, the Liebherr LB36-410 rig has been used to complete piles for the new bridge link. The machine has had success drilling through waterlogged ground and has helped to keep the project on schedule. Vietnamese ground engineering and foundations specialist contractor, Dua Fat Foundation Joint Stock Company has been using the Liebherr LB 36-410 rotary drillin
  • New German road tunnel proposed
    February 21, 2023
    An important new German road tunnel is being proposed.