Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • UK’s A14 upgraded route opening early
    October 14, 2019
    A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times. Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by
  • The UK’s A14 route is seeing a major upgrade
    June 14, 2018
    Work is progressing well on the project to upgrade the busy A14 route in the UK. A major milestone has been achieved with and important phase of the bridge installation having taken place. A 39m viaduct beam has been placed successfully for the bridge, which spans the River Ouse in Cambridgeshire. A key role in this work has been taken by the firm Cleveland Bridge UK. As part of Highways England’s £1.5 billion A14 Cambridge to Huntingdon improvement scheme, Cleveland Bridge was contracted by the A14 Integr
  • UK’s A14 widening project ramps up with a recruitment drive
    November 11, 2016
    Contractors are gearing up for one of the UK’s largest road projects, the 34km widening of the A14 between the town of Huntingdon and city of Cambridge. The €1.7 billion government-funded scheme will be delivered over four years by a joint venture between Skanska, Costain, Balfour Beatty and Carillion.
  • UK’s A14 route to open early
    February 11, 2020
    Highways England has announced that the UK’s A14 route is to open early.