Slovakia, Salini Impreglio to part ways over D1-Višňové tunnel work

Slovakia and the Italian-Slovak consortium of Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel. The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed
March 11, 2019 Read time: 2 mins

Slovakia and the Italian-Slovak consortium of 7809 Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel.

The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed by the Slovakian government and the 1116 European Union through the 1054 European Investment Bank.

Slovakia’s National Highway Company (5891 NDS) has been under heavy criticism over construction delays and cost projections for the work that was scheduled to be finished by the end of this year. According to Slovakian media, the consortium has three months to wrap up its work but has also agreed to pay money owed to subcontractors through a new bank guarantee.

Michaela Michalová, a spokesman for NDS, said a new contractor will emerge from a transparent competition in the coming months.

"It is our goal to complete the project by 2023 because it is financed with [European Union] funds," said Árpád Érsek, transport minister, as quoted by the Slovak News Agency SITA.

The original design and build contract was worth about €410 million when signed in 2014, according the a statement Salini Impregilo at the time. Construction was expected to take five and half years.

For more information on companies in this article

Related Content

  • Financial setbacks beset Slovakia’s highway development
    June 12, 2012
    Slovakian highway company NDS says that construction of the 13km Turany-Hubova highway may not be started in 2012. The previous Transport Ministry plan was to call the tender for this stretch in summer 2012. However, the EC has not yet approved the construction of this highway, with questions surrounding the protected area in the Velka and Mala Fatra mountains. If Slovakia does not get this approval, the country might have to chose the second option, which includes the tunnel Korbelka. The EC's decision is
  • Slovakian road tunnel plan
    January 18, 2023
    Slovakia’s new road tunnel is being planned.
  • Slovakian road protests likely over missing D3 sections
    September 1, 2017
    More road blockades are likely after Slovakia’s state motorway company NDS announced it will not tender for missing sections of the D3 motorway this year. Residents of some towns have blocked sections of roads this year urging the government to speed construction of the D3 to help; boost their local economies, according to Slovakian media.
  • Salini wins deal to build part of Poland’s S7 Expressway
    August 28, 2018
    Salini Impregilo has won a new contract worth about €250 million in Poland to design and build a section called Lot 3 of the S7 Expressway. Work on the four-lane 18.3km section between Widoma and Krakow will last 34 months, includes the construction of overpasses, bridges, animal crossings and a 2km viaduct. The S7 will cross Poland from Gdansk in the north to Krakow in the south. The client is the General Directorate of National Roads and Motorways (GDDKiA). Salini recently announced the sale of the plan