A solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover. The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity r
March 12, 2015 Read time: 2 mins
RSSA solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover.

The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity recommence, according to Business News Americas. The US$363 million project has been the focus for major negotiations between both parties over the last few months while a solution has been searched for. Earlier this year, work stalled and the consortium faced having its contract cancelled by the state road authority 2812 Invias. Meanwhile the consortium members were told they could face a ban from working on any state tenders for a five year period.

The Segundo Centenario consortium comprises 11 firms: Condux, Constructora Herreña Fronpeca Colombia, Álvarez y Collins, Constructora Carlos Collis, Constructora Montecarlo Vías, Túneles de Colombia, Construirte, Gaico Ingenieros Constructores, H&H Arquitectura and Feluca.

This new compromise deal means that the consortium has to complete the tunnel by the end of November 2016. An additional $125 million is being provided to pay for the completion work. The 8.5km tunnel will link Colombia’s capital Bogota with the country’s main port, Buenaventura, and was originally planned for completion by November 2014. The tunnel is around 75% complete and the project also includes the construction of a 24km highway. When the route is finished it will cut journey times for commuters and also for the many heavy trucks driving between the port and Bogota, as well as improving safety over the existing road.

For more information on companies in this article

Related Content

  • Cost rises again for Columbia’s unfinished La Linea tunnel
    February 3, 2015
    Columbia’s transport minister has said it will take nearly US$168 million and more than two years to finish the controversial La Linea tunnel. Natalia Abello Vives said the government has a “plan B” to finish the 8.65km tunnel, which, as World Highways reported in May, has less than a kilometre remaining to be constructed. It was originally scheduled to be open by last November. The La Linea tunnel project, or Segundo Centenario tunnel, crosses the central mountain range and forms part of the Bogota-B
  • Colombia’s troubled tunnel project completion due
    April 26, 2017
    The completion of work on Colombia’s troubled tunnel project is now finally in sight. A new contractor will be selected by Colombia's National Road Institute (Invias) to complete the last section of work required on the La Linea Tunnel. The winner of the tender process will be announced on 13th June 2017. An additional US$50 million is being budgeted by the Colombian authorities to complete the work. It is expected that in all, finishing the project will cost $86.6 million. Work still to be carried out incl
  • Further delays possible for Colombia tunnel
    July 21, 2016
    Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
  • Colombia tunnel project conclusion plan
    December 6, 2016
    Tendering is commencing for the final portion of works to complete Colombia’s La Linea tunnel project. Around 12% of the work on the tunnel still has to be completed, with the work expected to cost US$68.5 million. The tender is being carried out by Colombia's National Road Institute (Invias). The tunnel project has been delayed for a series of reasons. Colombian contractor Constructora Carlos Collins was constructing the tunnel but did not meet the necessary deadline. As a result, Invias opted to open the