Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • Slovakia: Strazov-Brodno D3 route around Zilnia to get EU funds
    May 10, 2016
    The European Union is providing nearly €202 million to finish the section of the D3 motorway between Strazov and Brodno around the city of Zilina in Slovakia. Zilnia is in north-west of Slovakia, around 200km from the capital Bratislava and close to the Czech and Polish borders. It is the fourth largest city of Slovakia with a population of around 85,000. The D3, formerly D18, is sometimes called the Kysuce Motorway. It was originally to be only a two-lane motorway in the Čadca - Slovak/Polish border
  • Polish plans progressing
    October 3, 2014
    Plans are moving forward for a series of key highway projects in Poland. One project involves constructing three sections of the new southern ring road around Polish capital Warsaw. Building the 18.5km stretch that comprises the three sections is expected to cost in the region of €1.6 billion.
  • Bulgaria continues with Struma motorway, Blagoevgrad to Krupnik
    September 14, 2017
    Bulgaria has started work on a 12.6km section of Struma motorway between the southwestern towns of Blagoevgrad and Krupnik. A consortium led by Bulgarian construction company Agromah is building the section under a contract worth just over €71 million, according to the regional development ministry.
  • Key Polish infrastructure project delivered 6 months ahead of schedule
    April 24, 2012
    Poland's most important infrastructure project of the past few years, a new 106 km section of the A2 motorway Segment II between Owiecko on the German border and Nowy Tomyol, opened this week, six months ahead of schedule.