Strabag closes in on Poland’s S8 Marki-Kobylka contract

Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I
August 19, 2019 Read time: 2 mins
945 Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio.  


Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by 1361 GDDKiA, Poland’s road authority.

Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by Intercor at nearly €65 million and one by and Budimex at just over €39 million.

GDDKiA expects to sign a contract in November with completion set for spring 2021.
 
The contract is one two that make up construction of a 15km section of the S8 expressway. The consortium from Salini was responsible for the implementation of the first contract. The second has already been completed.

More than 500km of the planned 565km S8 road have been built since construction started in 2003. It runs from Wrocław to Białystok via Łódź and the capital Warsaw.

Originally, the road was to continue to the border with Lithuania, but in 2009 the plans were changed and currently the S61 will branch off the S8 and go to the border.

The S8 section from Warsaw to the S61 interchange is planned to become part of the Via Baltica, a stretch of the European route E 67.

Via Baltica runs from the Czech Republic to Helsinki in Finland by way of Poland, Lithuania, Latvia and Estonia. It goes via Prague, Wrocław, Warsaw, Kaunas, Panevėžys, Riga, Tallinn and Helsinki. The final stretch between the Estonian capital Tallinn and the Finnish capital Helsinki is by ferry, a two-and-a-half hour crossing of the Gulf of Finland.

For more information on companies in this article

Related Content

  • Lidl by Lidl, more rental bikes in Berlin
    November 14, 2016
    German discount supermarket chain Lidl is to sponsor 3,500 new rental bicycles in Berlin. The bicycle system Lidl Bikes will be operated by DB Rent, a subsidiary of German railway provider Deutsche Bahn (DB), and be available from spring next year. DB Rent, which has been running rental bicycles for nearly 15 years, is operating around 10,000 bicycles in 50 German cities. The system of flexible borrowing will cover Berlin's S-Bahn commuter train region. But from the end of 2017 Lidl Bikes will face
  • Lidl by Lidl, more rental bikes in Berlin
    November 14, 2016
    German discount supermarket chain Lidl is to sponsor 3,500 new rental bicycles in Berlin. The bicycle system Lidl Bikes will be operated by DB Rent, a subsidiary of German railway provider Deutsche Bahn (DB), and be available from spring next year. DB Rent, which has been running rental bicycles for nearly 15 years, is operating around 10,000 bicycles in 50 German cities. The system of flexible borrowing will cover Berlin's S-Bahn commuter train region. But from the end of 2017 Lidl Bikes will face
  • Global sales of earth moving machinery surge 23% in 2018
    April 23, 2019
    Global sales of earth moving machinery in 2018 accelerated sharply – up 23% on 2017 to top out at 1 million units. The record result in 2018 was driven by a combination of several factors. One of these factors is investments in construction on a global scale in excess of €7,150 billion, as highlighted by data analysed by Prometeia for SaMoTer Outlook 2019, the sector observatory presented today at Veronafiere during the 5th edition of SaMoTer Day. The event is one of the stages in the run up to the 31st
  • Polish expressway project gets go ahead
    December 19, 2017
    With the official go ahead being given for a new expressway in Poland’s southern Silesia Region, tendering can now commence. This last stretch of the S1 expressway will run from Bielsko-Biala to Zwardon and will measure 8.5km long. Tendering is now starting for the project, which is expected to cost in the region of €351.25 million and should take two years to build. This new road project forms part of the 2014-2023 National Road Construction Programme.