Slovakia opens Levoca bypass of D1 motorway section

Slovakia has opened the 9.5km Levoca bypass, nearly completing the northern part of the D1 cross-country motorway. The remaining section between Bratislava and Kosice is expected to be open around 2020, with the Zilina, Presov and Ruzomberok bypasses yet to be built. The newly opened section of Janovce - Jablonov II includes the 600m tunnel Sibenik, as well as a slip road to Levoca and 12 road bridges. Construction works on the D1 section started in June 2012 by the consortium of Eurovia and Stavby M
December 4, 2015 Read time: 2 mins
Slovakia has opened the 9.5km Levoca bypass, nearly completing the northern part of the D1 cross-country motorway. The remaining section between Bratislava and Kosice is expected to be open around 2020, with the Zilina, Presov and Ruzomberok bypasses yet to be built.

The newly opened section of Janovce - Jablonov II includes the 600m tunnel Sibenik, as well as a slip road to Levoca and 12 road bridges.

Construction works on the D1 section started in June 2012 by the consortium of 3281 Eurovia and Stavby Mostov Slovakia. The cost is around €126 million, with the majority funded by European Union subsidies.

In June, 7808 Slovakian National Motorway Company NDS put out to tender two sections of the D1 near Presov and Kosice. Both tenders were published in the Official Journal of the European Union, with bid submission deadlines set for June 29.

The first section is the south-west D1 by-pass of Presov at nearly 8km long, including the construction of a 2km dual-tube road tunnel Presov and estimated to cost €443.4 million. The second section is the 14.5km Budimir to Bidovce stretch, with costs estimated at nearly €251.3 million.

Meanwhile, the government recently approved a €109 million reallocation to road construction.

For more information on companies in this article

Related Content

  • Bratislava bypass and Karpaty tunnel completion set for 2030
    June 18, 2018
    Slovakia’s national motorway company NDS expects that the Bratislava bypass on the D4 motorway together with the Karpaty tunnel will be completed around 2030. The D4 motorway is part of the trans-European transport network and will connect with the planned R7 expressway linking western and eastern Slovakia, and the existing D1 and D2 motorways”. Apart from construction works on part of the D4 motorway, another two stretches are planned on this link, including the 3.6km stretch from Devinska Nova Ves t
  • Slovakia, Salini Impreglio to part ways over D1-Višňové tunnel work
    March 11, 2019
    Slovakia and the Italian-Slovak consortium of Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel. The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed
  • Slovakia tenders for Visnove IT systems
    August 10, 2022
    The deal is likely to be worth around €71.5 million and bids can be submitted until October 25.
  • Slovakia highway projects due for completion
    September 2, 2015
    In Slovakia work on three sections of the D1 highway will be complete shortly. One of these is for a 9km section of the D1 from Janovce -Jablonov, which is built by the Czech firm Bogl and Krysl. A 9.5km section of the D1 from Janovce -Jablonov is being built by Eurovia and will be ready at the end of 2015. The 11.2km section of the D1 from Fricovce - Svinia is being built a consortium comprising Strabag and Doprastav and is scheduled for completion in October 2015. The 10.4km section of the R2 route from P