Slovakia and the Italian-Slovak consortium of Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel. The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed
March 11, 2019 Read time: 2 mins

Slovakia and the Italian-Slovak consortium of 7809 Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel.

The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed by the Slovakian government and the 1116 European Union through the 1054 European Investment Bank.

Slovakia’s National Highway Company (5891 NDS) has been under heavy criticism over construction delays and cost projections for the work that was scheduled to be finished by the end of this year. According to Slovakian media, the consortium has three months to wrap up its work but has also agreed to pay money owed to subcontractors through a new bank guarantee.

Michaela Michalová, a spokesman for NDS, said a new contractor will emerge from a transparent competition in the coming months.

"It is our goal to complete the project by 2023 because it is financed with [European Union] funds," said Árpád Érsek, transport minister, as quoted by the Slovak News Agency SITA.

The original design and build contract was worth about €410 million when signed in 2014, according the a statement Salini Impregilo at the time. Construction was expected to take five and half years.

For more information on companies in this article

Related Content

  • Delays ahead for Slovakia’s Visnove tunnel
    September 5, 2018
    Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022. The recent announcement came as the ministry agreed to an extension to the construction permit held by Salini Impregilo for work on the twin-tube tunnel. The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company NDS.
  • Bids for Višňové Tunnel's IT being evaluated
    March 31, 2023
    The contract, in Slovakia, also includes IT equipment for the D1 motorway stretch Lietavska Lucka - Visnove - Dubna Skala of which the tunnel is a part.
  • Višňové Tunnel delays continue
    June 21, 2022
    What will be Slovakia’s longest tunnel at 7.5km is facing more technical issues, according to the contractor Skanska.
  • Date set to complete D1 Višňové Tunnel section
    July 20, 2023
    The D1 section between Lietavská Lúčka and Dubná Skala in Slovakia includes the partially completed 7.5km twin-tube Višňové Tunnel - to be the country's longest.