Slovakia opens Levoca bypass of D1 motorway section

Slovakia has opened the 9.5km Levoca bypass, nearly completing the northern part of the D1 cross-country motorway. The remaining section between Bratislava and Kosice is expected to be open around 2020, with the Zilina, Presov and Ruzomberok bypasses yet to be built. The newly opened section of Janovce - Jablonov II includes the 600m tunnel Sibenik, as well as a slip road to Levoca and 12 road bridges. Construction works on the D1 section started in June 2012 by the consortium of Eurovia and Stavby M
December 4, 2015 Read time: 2 mins
Slovakia has opened the 9.5km Levoca bypass, nearly completing the northern part of the D1 cross-country motorway. The remaining section between Bratislava and Kosice is expected to be open around 2020, with the Zilina, Presov and Ruzomberok bypasses yet to be built.

The newly opened section of Janovce - Jablonov II includes the 600m tunnel Sibenik, as well as a slip road to Levoca and 12 road bridges.

Construction works on the D1 section started in June 2012 by the consortium of 3281 Eurovia and Stavby Mostov Slovakia. The cost is around €126 million, with the majority funded by European Union subsidies.

In June, 7808 Slovakian National Motorway Company NDS put out to tender two sections of the D1 near Presov and Kosice. Both tenders were published in the Official Journal of the European Union, with bid submission deadlines set for June 29.

The first section is the south-west D1 by-pass of Presov at nearly 8km long, including the construction of a 2km dual-tube road tunnel Presov and estimated to cost €443.4 million. The second section is the 14.5km Budimir to Bidovce stretch, with costs estimated at nearly €251.3 million.

Meanwhile, the government recently approved a €109 million reallocation to road construction.

For more information on companies in this article

Related Content

  • Slovakia’s D1 highway project underway
    August 11, 2022
    Work on Slovakia’s D1 highway project is underway.
  • Slovakia looking for more road financing
    June 13, 2017
    The Slovak government is exploring options for road financing after 2020, according to the media.
  • Delays plague Slovakia’s D1 motorway work
    May 12, 2017
    Slovakia is reporting delays to works on the D1 motor, the country’s major east-west corridor and part of several pan-European routes, including the E50. The planned 2020 completion of the D1 motorway linking Bratislava - Kosice could be 2021. There are reported technical complications to the section between Lietavska Lucka - Dubna Skala stretch with the Visnove tunnel near Zilina is experiencing complications. Work by the consortium of OHL and Vahostav on the D1 stretch Hubova – Ivachvova is suspended due
  • Bratislava bypass and Karpaty tunnel completion set for 2030
    June 18, 2018
    Slovakia’s national motorway company NDS expects that the Bratislava bypass on the D4 motorway together with the Karpaty tunnel will be completed around 2030. The D4 motorway is part of the trans-European transport network and will connect with the planned R7 expressway linking western and eastern Slovakia, and the existing D1 and D2 motorways”. Apart from construction works on part of the D4 motorway, another two stretches are planned on this link, including the 3.6km stretch from Devinska Nova Ves t