Slovakia: early 2017 restart for work on the Cebrat Tunnel

Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
May 27, 2016 Read time: 2 mins
Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017.

But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding.

Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer.

The tunnel is part of the D1 motorway section between Hubova and Ivachvova, which was supposed to be completed in June next year but will probably be completed in 2020.

Brecely also recently said that delays could affect construction of three motorway stretches, one section of the D3 and two of the D1.

Meanwhile the state-owned national motorway company 5891 NDS said that some 87% of land needed for the public-private partnership Bratislava Bypass has been expropriated. Construction is about to start on one section of the Bratislava bypass after the contract was finally sealed with the consortium Obchvat Nula (Bypass Zero), led by 930 Cintra of Spain and including 2378 Macquarie from Australia and 3976 Porr of Austria.

Media reports said that Cintra has 12 weeks to secure financing for the 30-year public-private partnership likely to cost upwards of €1.9 billion.

For more information on companies in this article

Related Content

  • Breakthrough near for Čebrať Tunnel
    December 17, 2021
    The 3.5km-long tunnel through Slovakia’s Čebrať Hills is part of the D1 Ružomberok bypass.
  • Slovakia tunnel sections underway but some delays
    January 23, 2018
    The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against th
  • Cost of D1 section Hubova-Ivachnova rises 40%
    August 3, 2023
    In Slovakia, the 15km Ružomberok bypass, including the 3.6km Čebrať Tunnel, is now €93 million more expensive than nine years ago.
  • Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section
    December 13, 2017
    Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the