Serbia ponders penalties for Azvirt over Ljig-Preljina delays

The Serbian government has said it could issue penalties to the Azerbaijani construction company Azvirt for delays to work on the Ljig-Preljina Corridor 11 motorway project. Completion was set for the middle of next month. But last month the government said delays of around a month were due to problems construction the tunnel and bridge sections. The new route is expected to open around 40 days later than originally expected as a result.
September 9, 2016 Read time: 1 min

The Serbian government has said it could issue penalties to the Azerbaijani construction company 5414 Azvirt for delays to work on the Ljig-Preljina Corridor 11 motorway project.

Completion was set for the middle of next month. But last month the government said delays of around a month were due to problems construction the tunnel and bridge sections. The new route is expected to open around 40 days later than originally expected as a result.

Minister of Transport, Zorana Mihajlovic, had stated that the government will want an explanation from the investor, Serbian roads company 3235 Koridori Srbije.

For more information on companies in this article

Related Content

  • Mombasa-Tanga link faces delays over design changes
    April 10, 2018
    Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga. The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway. However, the African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.
  • Pocitelj Bridge reaches banks of Neretva River
    August 21, 2023
    Contractors are working to correct a concrete issue on a section of the 100m-long continuous prestressed girder bridge across the Neretva River in Bosnia and Herzegovina.
  • Work on Serbian highway to be carried out by Chinese company Shandong High Speed Group
    December 10, 2013
    Chinese firm Shandong High Speed Group is to carry out a portion of the construction activity for Serbia’s Corridor 11 highway. The company will commence work on the section between Obrenovac to Ub and from Lajkovac to Ljig shortly. The agreement was signed between the Shandong High Speed Group and the Serbian Government. Work on the project is due to for completion within 37 months. Exactly which portions of the construction work on these sections has not been revealed however. At present several sections
  • Key Polish infrastructure project delivered 6 months ahead of schedule
    April 24, 2012
    Poland's most important infrastructure project of the past few years, a new 106 km section of the A2 motorway Segment II between Owiecko on the German border and Nowy Tomyol, opened this week, six months ahead of schedule.