Poland: Ministry decides to build missing section of A1 motorway

The Polish government said that it will complete the final 80km section of the A1 motorway at a cost of around €830 million. Money will come out of the National Road fund (KFD), according to the Ministry of Infrastructure and Construction. The missing section stretches from Tuszyn to Czestochowa and the government will choose contractors in September 2017. Completion is set for 2020. Earlier this year, Strabag was awarded a contract to build a further section of the A1 motorway, around 16.7km betwe
October 24, 2016 Read time: 2 mins
The Polish government said that it will complete the final 80km section of the A1 motorway at a cost of around €830 million.

Money will come out of the National Road fund (KFD), according to the Ministry of Infrastructure and Construction.

The missing section stretches from Tuszyn to Czestochowa and the government will choose contractors in September 2017. Completion is set for 2020.

Earlier this year, 945 Strabag was awarded a contract to build a further section of the A1 motorway, around 16.7km between the Zawodzie Junction and Woźniki Junction.

The €108 million project is expected to be opened to traffic in the second half of 2019. The section of motorway is part of the A1 running from Gdansk in the north to the Czech border. It forms part of European Route 75. In addition to the concrete roadway, Strabag will also build the Woźniki Junction as well as bridges and several adjoining local roads.

For more information on companies in this article

Related Content

  • Budimex consortium win Poland’s Ostroda ringroad court case
    March 18, 2015
    A district court in the Polish town of Olsztyn has ruled in favour of a consortium of Budimex and Ferrovial Agroman which challenged the awarding of a ringroad contract to a rival. The ruling means that the Salini consortium’s winning bid for the construction of a ringroad around Ostroda is overturned on the basis that it was ineffectually low. This means that the contract will go to the Budimex consortium which proposed to build the road for around €223 million. Polish builder Budimex is the consortium's m
  • Tender process underway for Polish road projects
    August 18, 2014
    The tender process is underway for two major projects in Poland. One project involves constructing three sections of the new southern ring road around Polish capital Warsaw. Building the 18.5km stretch that comprises the three sections is expected to cost in the region of €1.6 billion. The Polish General Directorate for National Roads and Motorways (GDDKiA) says that bids have to be submitted by 10th October 2014. The A section will be some 4.6km long, the B section 6.45km long, whilst the C section will be
  • Czech D35 section deal for Mott MacDonald
    April 23, 2024
    PricewaterhouseCoopers, Mott MacDonald, White & Case and SIEBERT + TALAŠ are part of the winning consortium for the Mohelnice-Opatovec stretch.
  • Four offers for Sibiu-Pitesti A1 motorway Lot 4 section
    September 4, 2019
    Main Site Taxonomy WH5 Sub Taxonomy ES08 Image supplied No Needs XSP Romania’s national road agency reports that it has four offers for both the design and construction of Lot 4 of the Sibiu-Pitesti A1 motorway. The National Company for the Administration of Road Infrastructure (CNAIR) said the value of the deal is around €427.5 million. Construction is likely to take 60 months - 16 months for design work and 44 for construction. The bidders are from China, Turkey, Austria and Italy. Lot